Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
Quarterly Activities Report
For the quarter ended 30 September 2025
31 OCTOBER 2025
MCB PROJECT ADVANCING TOWARD OPERATIONAL READINESS
HIGHLIGHTS
• Feasibility Study update and Front-End Engineering Design (“FEED”) are progressing on
schedule, supported by promising drilling results, laying the groundwork for operational
readiness.
• Second drawdown of bridge loan facility from Maharlika Investment Corporation (“MIC”)
providing critical financial support to the FEED and updated Feasibility Study.
• Closing cash as of 30 September 2025 of A$2.39 million of which A$1.49 million is held
by MMCI.
ASX RELEASE | QUARTERLY REPORT | 30 SEPTEMBER 2025 2
Celsius Resources Limited (“Celsius” or the “Company”) (ASX, AIM: CLA) is pleased to provide
the following summary of the Company’s activities for the quarter ended 30 September 2025.
PROJECTS
MAALINAO-CAIGUTAN-BIYOG COPPER-GOLD PROJECT (“MCB PROJECT” OR THE
“PROJECT”), PHILIPPINES
Makilala Mining Company, Inc. (“MMCI”), the Celsius Resources affiliate company in the
Philippines, is actively progressing the FEED and updating the MCB Project’s Feasibility Study
to advance early development works1
.
The FEED program remains on track, with the current scope of work progressing steadily
towards its targeted completion in December. Parallel to this, the Feasibility Study update is
being actively informed by ongoing field work at the Project site, ensuring that the latest site
investigations are integrated into the evolving development strategy. Ausenco has issued an
Interim Study Report to the Company which outlined key enhancements in several technical
areas. Notable improvements were identified in the site layout, underground mine design,
process plant configuration, and materials handling systems. These refinements are expected
to yield more efficient operating costs and contribute to a stronger overall economic profile
for the Project. Updated commodity forecasts are also anticipated to positively impact the
financial model.
In parallel, the Geotechnical and Hydrogeological Drilling campaign is well advanced towards
producing a comprehensive surface and subsurface data and model that will enhance the
underground mine plan, refine the process plant layout, and improve surface infrastructure
design. The results will play a critical role in guiding updates to the Feasibility Study.
During the quarter, one hole from the current drilling program was a metallurgical test hole
that delivered better-than-expected results compared to the resource model, confirming
consistent high-grade copper mineralisation. Significant assay results contain 113.1m @
1.32% Cu and 0.41g/t Au from 8.1m, including 54.6m @ 1.84% Cu and 0.74m g/t Au from
60.4m. These findings reconfirmed the mineralisation of the target zone and will inform
upcoming test work and resource assessment.2
Table 1. Significant intersection from drill hole MTPH-001
1
ASX/AIM announcement 27 June 2025
2
ASX/AIM announcement 15 September 2025
ASX RELEASE | QUARTERLY REPORT | 30 SEPTEMBER 2025
3
Figure 1. Location of drill hole MTPH-001 relative to recent and historical diamond drilling at MCB3
Figure 2. Cross section (see location at Figure 1) showing drill hole MTPH-001 in proximity to MCB-042
and MCB-043, highlighting significant assay results (looking northeast)4
These results reinforce the expectation that the Project will deliver optimal value to
stakeholders, including investors, shareholders, and the community.
3
ASX/AIM announcements 19 May 2025, 27 June 2025 and 15 September 20025
ASX RELEASE | QUARTERLY REPORT | 30 SEPTEMBER 2025
4
SOCIAL DEVELOPMENT
As part of the Company’s commitment under the Social Development and Management
Program (“SDMP”), several key initiatives were also implemented to build the capacities of the
host community and support community development:
Stakeholder Engagement
Monthly meetings of the joint Barangay Balatoc-Council of Elders were consistently
facilitated, serving as a vital platform for presenting technical, environmental and social
updates and addressing project-related concerns. These gatherings fostered transparency,
open communication, and a stronger sense of partnership between the Company and the
community.
Community-Based Skills Training
A total of 130 host community members completed various skills training implemented by the
Company in partnership with the Technical Education and Skills Development Authority
(“TESDA”) and local service providers. These training courses were designed to equip
participants with practical, in-demand competencies that enhance employability, strengthen
livelihood opportunities and promote financial self-reliance within the community. The
programs covered a range of technical and vocational disciplines aligned with local economic
opportunities, enabling training graduates to pursue jobs, start small businesses, or contribute
to ongoing infrastructure projects4
. The financial literacy and management trainings will help
participants effectively manage income, savings and small enterprises.
As part of the practical application component, trainees contributed to actual construction
and maintenance tasks, including electrical-related masonry work at local schools and
churches. These outputs served dual purposes: reinforcing the trainees’ learning through real-
world practice and directly improving community facilities. The initiative reflects a strategic
approach to workforce development, empowering individuals with marketable skills while
simultaneously addressing local development priorities.
Table 2. Balatoc Community-Based Skills Training Completers, 3Q 2025
Community-Based Skills Training Batch
No. of
completers
Financial Literacy and Management
1 22
2 15
Electrical Installation and Maintenance
1 24
2 23
Masonry
1 22
2 24
Total 130
Educational Assistance and Scholarship
Educational assistance and scholarship was extended to a total of 254 beneficiaries from
Barangay Balatoc, reflecting a strong commitment to uplifting the community through access
to higher education and professional advancement. Of these, 202 were college students
pursuing undergraduate degrees across various fields, while 30 were enrolled in graduate
school programs, furthering their academic specialisation and research capabilities.
Additionally, 22 beneficiaries received support for their licensure examination review where
4
ASX/AIM announcement 7 October 2024
ASX RELEASE | QUARTERLY REPORT | 30 SEPTEMBER 2025
5
three reviewees passed their licensure exams in Medical Technology, Criminology, and Social
Work—marking a significant milestone in their professional journeys and contributing to the
pool of qualified practitioners in the region.
Furthermore, full scholarships were awarded to two students pursuing degrees in Mining
Engineering. This targeted support not only eases the financial burden of their studies but also
aligns with the strategic goal of developing local expertise in the mining sector. By investing
in future professionals, the program helps ensure that the community can actively participate
in and benefit from industry-related opportunities.
ENVIRONMENTAL MANAGEMENT
Several key plans and program documents were developed and submitted to the national
government in line with the MCB Project’s Environmental Compliance Certificate (“ECC”).
These include the Information, Education, and Communications Plan, Hazardous Chemicals
Management Plan, Carbon Sink Program, and the Biodiversity Management Plan.
Also, a comprehensive internal gap assessment was carried to strengthen the Company’s
Environmental Management System ensuring readiness for ISO 14001 certification. A series
of employee awareness sessions on Environmental Management Systems were actively
sustained. These sessions focused on harmonising procedures across teams, fostering a
culture of environmental responsibility and reinforcing consistent, effective practices
throughout the organisation.
ANCILLARY PERMITS
Water Permit
The Philippine National Water Resources Board (“NWRB”) has granted a conditional water
permit, authorising the initiation of water usage activities—an essential step in preparing for
the project’s operational requirements. This approval is subject to strict adherence to the
conditions stipulated under the Water Code of the Philippines5
.
As part of its compliance obligations, MMCI is required to install calibrated water measuring
devices and submit quarterly utilisation reports to the NWRB. These reports serve as a basis
for the NWRB to validate actual water withdrawals, evaluate the long-term sustainability of the
water source, and ensure that project-related water use does not infringe upon existing water
rights or compromise the needs of surrounding communities. The transition from a
conditional to a permanent water permit will depend on MMCI’s continued and satisfactory
compliance with these monitoring and reporting requirements.
Tree-Cutting Permit
Preparatory activities are currently in progress to fulfill the documentary requirements for the
Tree Cutting Permit application. This permit is an essential regulatory step for initiating site
development. This process is being carried out along the finalisation of the optimised mine
design and layout, which will identify specific zones where tree removal may be necessary to
accommodate project infrastructure.
Construction Permit
A draft Memorandum of Agreement and Implementation Plan has been developed, aimed at
streamlining the construction permitting process in line with the Project schedule.
Forthcoming consultations with the Local Government Unit of Pasil will help refine the
provisions of the agreement and facilitate its formalisation.
5 Presidential Decree No. 1067 and its Implementing Rules and Regulations.
ASX RELEASE | QUARTERLY REPORT | 30 SEPTEMBER 2025
6
FUNDING SUPPORT
To support these ongoing activities, the Company has made a third drawdown of funds from
the Maharlika Investment Corporation’s (“MIC”) First OLSA bridging loan. As at the date of
this report, MMCI had drawn US$6 million of the US$10 million First OLSA to fund MMCI MCB
Project related activities6
.
Celsius and MMCI have been actively engaging with investors to explore funding options for
the MCB Project. MIC has continued to express interest in participating through an equity
investment in the MCB Project. A non-binding Memorandum of Undertaking was signed with
Kiri Industries, signaling potential investment collaboration. Discussions with prospective
investors remain ongoing, with a focus on structuring both debt and equity financing
solutions. The Company is confident that a comprehensive financing package for the Project
can be achieved in the next quarter.
BOTILAO COPPER-GOLD PROSPECT
MMCI has formally submitted its Exploration, Environmental, and Community Development
Programs as part of the requirements for the first renewal of its exploration permit. The
Exploration Work Program outlines planned geological activities and resource evaluation
strategies, while the Environmental Program details mitigation measures during exploration
activities including monitoring protocols, and compliance with national environmental
regulations. The Community Development Program highlights initiatives aimed at assisting
the host community with its community development needs and strengthen community
relations.
The renewal of the exploration permit is ongoing and MMCI expects that the first renewal will
be finalised by December 2025. Expenditure on this project is being carefully managed to
focus on essential activities that sustain meaningful engagement with the community, local
government units, and regulatory agencies, thereby maintaining project momentum and
stakeholder confidence as the Company prioritizes the MCB Project.
OPUWO COBALT PROJECT, NAMIBIA
As disclosed previously to the market, the Company has opened its data room to parties
interested in acquiring the Company’s Opuwo Cobalt project in Namibia (“Opuwo”). Several
parties have expressed interest in acquiring the Project and are continuing with their due
diligence. As of the date of this report, no binding agreement has been reached and, although
discussions are continuing, there can be no certainty that any binding agreement will be
reached or the timing of any such agreement.
The Opuwo tenement permit EL4346 is due for renewal. The Company has lodged the
necessary documentation to have the permit renewed with the Ministry of Mines. The
tenement remains active until such time that it is renewed by the Ministry of Mines and the
Company is continuing discussions on the renewal process with the Namibian authorities.
6 ASX announcement 7 August 2025
ASX RELEASE | QUARTERLY REPORT | 30 SEPTEMBER 2025
7
SAGAY COPPER-GOLD PROJECT, PHILIPPINES
Tambuli Mining Company, Inc. (“TMCI”), a wholly owned Philippine subsidiary of Celsius in the
Negros Islands, is actively engaging with the Department of Environment and Natural
Resources-Environmental Management Bureau on the evaluation and approval of its
Environmental Impact Statement (“EIS”) for the Sagay Copper-Gold Project (“Sagay Project”).
The EIS serves as the foundation for securing an Environmental Compliance Certificate
(“ECC”), as mandated by the Philippine Mining Act of 19957
. This certification ensures that the
development plans and engineering designs submitted under the Declaration of Mining
Project Feasibility (“DMPF”) are technically viable, environmentally responsible, and socially
acceptable. Expenditure on the Sagay Project is being carefully managed to focus on essential
activities that sustain meaningful engagement with the community, local government units,
and regulatory agencies, thereby maintaining project momentum and stakeholder confidence
as the Company prioritizes activities at the MCB Project.
CULLARIN WEST PROJECT, NSW
The Company has previously announced the intention to dispose of its interest in this project8.
No development activities were conducted during the quarter.
CORPORATE AND EXPENDITURE
A General Meeting of Shareholders was held on 7 August 2025 where shareholders approved
the issue of additional free-attaching options to participants of Tranche 2 of the placement9
announced on 10 March 2025. The additional free-attaching options were issued on 14
August 2025.
The Company released its Annual Report on Monday 29 September 202510
, and post quarter
end on 13 October 2025, the Company announced that its Executive Chairman, Julito “Sarge”
Sarmiento, will retire at the Company’s Annual General Meeting to be held on 26 November
2025.
Cash Position
At the end of the quarter, the Company held approximately A$2.39 million in cash reserves, of
which A$1.496 million was held in MMCI.
ASX ADDITIONAL INFORMATION
The Company provides the following information pursuant to ASX Listing Rule requirements:
• ASX Listing Rule 5.3.1:
Approximately A$4.367 million was spent on exploration expenditure during the
quarter, primarily relating to the development of the MCB Project.
• ASX Listing Rule 5.3.2:
Nil was spent on mine production and development activities during the quarter.
• ASX Listing Rule 5.3.5:
7
https://lawphil.net/statutes/repacts/ra1995/ra_7942_1995.html
8
ASX/AIM announcement 31 January 2023
9
ASX/AIM announcement 9 May 2025
10
ASX/AIM announcement 29 September 2025
ASX RELEASE | QUARTERLY REPORT | 30 SEPTEMBER 2025
8
The Company advises that there were approximately A$537k in payments made to
related parties of the Company and their associates during the quarter. Approximately
A$149k was for Director and consultancy fees, A$282k was for MMCI management
fees and employment costs, and A$105k was for legal fees to Sarmiento Loriega Law
Office for which Julito Sarmiento (CLA Chairman and MMCI President) is a founding
partner.
Tenement Table: ASX Listing Rule 5.3.3 Mining tenement interests held at the end of the
quarter and their location
PERMIT
NAME
PERMIT
NUMBER
REGISTERED
HOLDER /
APPLICANT
PERMIT
STATUS
PERMIT
EXPIRY
INTEREST /
CONTRACTUAL
RIGHT
New South Wales
Cullarin West EL 8996
Cullarin Metals
Pty Ltd
Granted 17/08/2026 100%
Namibia
Opuwo EL 4346
Gecko Cobalt
Holdings
Granted 10/10/2025 95%
Philippines
Maalinao-
Caigutan-
Biyog
MPSA-356-
2024-CAR
Makilala Mining
Company Inc.
Granted 13/03/2049 40%
Botilao
EP-011-2023-
CAR
Makilala Mining
Company Inc.
Complying with
requirements for
renewal
29/09/2025* 40%
Panaon
EXPA-000127-
VIII
PDEP, Inc.
Complying with
further
requirements
TBA 100%
Sagay EP-000003-VI
Tambuli Mining
Company Inc.
Granted
Automatic
extension
until the
approval of
the
DMPF/MPSA
100%
* December 2025 is the target issuance of the first renewal.
The mining tenement interests acquired during the quarter and their location:
Nil.
Beneficial percentage interests held in farm-in or farm-out agreements at the end of the
quarter:
Not applicable.
Beneficial percentage interests in farm-in or farm-out agreements acquired or disposed of
during the quarter:
Nil.
This announcement has been authorised by the Board of Directors of Celsius Resources Limited.
ASX RELEASE | QUARTERLY REPORT | 30 SEPTEMBER 2025
9
The information contained within this announcement is deemed by the Company to constitute
inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 as it
forms part of UK Domestic Law by virtue of the European Union (Withdrawal) Act 2018.
For further information contact:
Celsius Resources Limited
Neil Grimes P: +61 8 9324 4516
E: info@celsiusresources.com.au
W: www.celsiusresources.com
Multiplier Media
(Australian Media Contact)
Jon Cuthbert M: +61 402 075 707
E: jon.cuthbert@multiplier.com.au
Zeus Capital Limited
(Nominated Adviser & Broker)
Harry Ansell/James Joyce/James
Bavister
P: +44 (0) 20 3 829 5000
Zeus Capital Limited (“Zeus”) is the Company’s Nominated Adviser and is authorised and
regulated by FCA. Zeus’s responsibilities as the Company’s Nominated Adviser, including a
responsibility to advise and guide the Company on its responsibilities under the AIM Rules for
Companies and AIM Rules for Nominated Advisers, are owed solely to the London Stock
Exchange. Zeus is not acting for and will not be responsible to any persons for providing
protections afforded to customers of Zeus nor for advising them in relation to the proposed
arrangements described in this announcement or any matter referred to in it.
Competent Persons Statement
Information in this report relating to Exploration Results and Mineral Resources for the MCB
Project and the Sagay Project is based on information compiled, reviewed and assessed by
Mr. Steven Olsen, who is a Member of the Australasian Institute of Mining and Metallurgy and
the Australian Institute of Geoscientists. Mr. Olsen is a consultant to Celsius Resources
Limited and has sufficient experience which is relevant to the style of mineralisation and type
of deposit under consideration and to the activity which he is undertaking to qualify as a
Competent Person as defined by the 2012 Edition of the Australasian Code for reporting of
Exploration Results, Mineral Resources and Ore Reserves. Mr. Olsen consents to the inclusion
of the data in the form and context in which it appears.
For the information in this announcement that relates to exploration results that have been
previously released to ASX, the Company confirms that it is not aware of any new information
or data that materially affects the information included in the original ASX announcement and
that all material assumptions and technical parameters continue to apply.
The information in this Report that relates to the estimate of Mineral Resources for the Opuwo
Project is based upon, and fairly represents, information and supporting documentation
compiled by Mr Kerry Griffin, a Competent Person, who is a Member of the Australian Institute
of Geoscientists (AIG). Mr Griffin is a Principal Geology Consultant at Mining Plus Pty Ltd and
an independent consultant engaged by Celsius Resources Pty Ltd for this work and has
sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a Competent Person as
ASX RELEASE | QUARTERLY REPORT | 30 SEPTEMBER 2025
10
defined in the 2012 edition of the “Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves” (the JORC Code). Mr Griffin consents to the inclusion
in this announcement of matters based on his information in the form and context in which it
appears.
The Company confirms that it is not aware of any new information or data that materially
affects the Mineral Resource for the MCB11
Project, the Sagay12
Project or the Opuwo13
Project. The Company also confirms that all material assumptions and parameters
underpinning the Mineral Resource estimate continue to apply and have not materially
changed. Please note that as at the date of this announcement there are studies ongoing to
update the Feasibility Study for the MCB Project and to complete the Front-End Engineering
and Design. These studies are scheduled for completion by December 2025.
Forward Looking Statements
Some of the statements appearing in this announcement may be in the nature of forward-
looking statements. You should be aware that such statements are only predictions and are
subject to inherent risks and uncertainties. Those risks and uncertainties include factors and
risks specific to the industries in which the Company operates and proposes to operate as
well as general economic conditions, prevailing exchange rates and interest rates and
conditions in the financial markets, among other things. Actual events or results may differ
materially from the events or results expressed or implied in any forward-looking statement.
No forward-looking statement is a guarantee or representation as to future performance or
any other future matters, which will be influenced by a number of factors and subject to
various uncertainties and contingencies, many of which will be outside the Company’s control.
The Company does not undertake any obligation to update publicly or release any revisions to
these forward-looking statements to reflect events or circumstances after today's date or to
reflect the occurrence of unanticipated events. No representation or warranty, express or
implied, is made as to the fairness, accuracy, completeness or correctness of the information,
opinions or conclusions contained in this announcement. To the maximum extent permitted
by law, none of the Company’s Directors, employees, advisors, or agents, nor any other person,
accepts any liability for any loss arising from the use of the information contained in this
announcement. You are cautioned not to place undue reliance on any forward-looking
statement. The forward-looking statements in this announcement reflect views held only as
at the date of this announcement.
11 Refer to ASX announcement dated 12 December 2022 for an updated JORC compliant Mineral Resource Estimate.
12 Refer to ASX/AIM announcement dated 6 February 2024 for the updated Mineral Resource Estimate for the Sagay Project.
13 Refer to ASX announcement dated 1 July 2021 for the updated Mineral Resource Estimate for the Opuwo Project.
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Celsius Resources Limited
ABN Quarter ended (“current quarter”)
95 009 162 949 30 September 2025
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (249) (249)
(e) administration and corporate costs (363) (363)
1.3 Dividends received - -
1.4 Interest received 1 1
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(611) (611)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment (107) (107)
(d) exploration & evaluation (4,367) (4,367)
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
(f) mine development (see note 6) - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received - -
2.5 Other (provide details if material) - -
2.6 Net cash from / (used in) investing
activities
(4,474) (4,474)
3. Cash flows from financing activities
- -
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
- -
3.5 Proceeds from borrowings 3,182 3,182
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (provide details if material) - -
3.10 Net cash from / (used in) financing
activities
3,182 3,182
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
4,369 4,369
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(611) (611)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(4,474) (4,474)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
3,182 3,182
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
(76) (76)
4.6 Cash and cash equivalents at end of
period
2,390 2,390
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 894 1,517
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other (held by MMCI) 1,496 2,852
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
2,390 4,369
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
255
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
282
- Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and
an explanation for, such payments.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities 25,135 6,054
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end 19,081
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
Share Placement Agreement, Celsius and Patras have entered into a Committed Equity
Facility Agreement which will provide Celsius with a further funding facility Celsius is not
required to draw down on the Facility and there is no minimum amount contemplated. The
Facility enables the Company to conditionally access further capital to fund its project
portfolio in the Philippines and the Company’s ongoing working capital. The Facility is
structured so that the timing of any or all drawdowns (and therefore an acceptable issue
price of any shares issued under the agreement) are entirely at Celsius’ discretion. The
facility matures in September 2026.
Under the terms of the Facility, Celsius may, at its discretion, place new ordinary shares in
the Company with Patras up to a total of A$10 million over the next 24 months. Celsius may
draw in traches of up to A$5 million at its full discretion, and up to A$3 million with mutual
consent which may be further increased by up to 15% by Patras. The Facility may be
terminated by the Company prior to completion of the two-year term without penalty, and
the Facility does not restrict Celsius obtaining any form, or combination, or equity or debt
financing from third parties or any other source.
For each placement under the Facility, Celsius can nominate a price in which it is willing to
place shares to Patras (or its nominee) provided it is not below A$0.01 per share