Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
Quarterly Activities Report
For the quarter ended 31 March 2026
1
30 April 2026
Celsius Resources Limited (“Celsius” or the “Company”) (ASX, AIM: CLA) continued to
advance the Maalinao-Caigutan-Biyog Copper-Gold Project (“MCB Project”) during the
March 2026 Quarter (“Quarter”) with the following recent milestones and events occurring:
Appointment of Managing Director
Bardin Davis was appointed as Managing Director of Celsius on 2 April 2026.
His appointment followed his role as a strategic advisor to the Company’s Board between
January and March 2026.
Bardin has ~30 years of investment banking and corporate experience within the mining
and energy sectors. He was the CEO of ASX listed Peak Rare Earths Limited (“Peak”) for ~5
years and is a former CFO of UPC/AC Renewables Australia (now ACEN Australia). During
• Appointment of Bardin Davis as Managing Director
• Search initiated for a new Non-Executive Chair
• Commencement of a Grant Samuel led MCB Project structured financing process
• Planned restructuring of MMCI to support enhanced Celsius economics
• Completion of ~A$9.3m equity raising
• Delivery of a DFS supporting a technically and economically enhanced MCB Project
• Continued momentum across key MCB Project workstreams:
o Strategic planning around underground mine development
o EPC tendering for the Process Plant
o Progress on planning for the Main Access Road
o Strong stakeholder engagement and support initiatives across skills training,
education and health
o Strengthening of the environmental management system
• Renewal of the exploration permit for the Botilao Copper-Gold Prospect
• Continued progress on the sale process for the non-core Opuwo Project in Namibia
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
2
his banking career he spent almost 12 years in Asia and worked on a broad range of
international advisory, capital market and financing transactions. He has held senior
Australian and regional investment banking roles with Macquarie Capital, HSBC and ABN
AMRO.
Managing Director,
Bardin Davis
During his time with Peak he oversaw a project financing process,
the execution of a binding offtake agreement, the securing of a
special mining licence and an investment framework agreement
with the Government of Tanzania, the delivery of a BFS Update
and FEED Study and a sale of the company that delivered a 269%
takeover premium and a ~330% premium after accounting for
the value of a concurrent entitlement offer1
.
Neil Grimes has agreed as part of a handover process to continue his role as an Executive
Director until the 22 July 2026, after which he will revert to a Non-Executive Director.2 3
Search initiated for Non-Executive Chair
Swann & Skein, a leading executive search firm, was appointed to advise on and facilitate
a comprehensive search process for a Non-Executive Chair.
This search, which is underway, is focused on candidates with the requisite leadership,
sector experience, and governance expertise to guide Celsius towards a Final Investment
Decision (“FID”) and the successful development of the MCB Project.
Following the appointment of a Non-Executive Chair, it is expected that a broader board
review will be undertaken.
MCB Project funding
Following the receipt of strong interest in financing the MCB Project, Grant Samuel Capital
Advisory Pty Limited (“Grant Samuel”) was appointed to lead a structured financing
process for the MCB Project.4
The funding process encompasses three streams:
• Offtake-linked financiers – focused on a targeted list of mining funds and trading
houses;
• Philippine and project finance banks – covering international, regional and Philippine
banks that are active in mining project financing; and
1
See ASX / AIM announcement – Appointment of Managing Director and search for Non-Executive Chair on 2 April
2026
2
In addition to his position as an Executive Director of Celsius and a director of a number of its subsidiaries, Neil
also holds positions with the following entities: Mannerim Capital Pty Ltd (Australia), Swan Bay Investments Pty Ltd
(Australia), Plentex Limited (Australia), Rizal Resources (Canada) and TMC Tribal Mining Corporation (Philippines)
3
See ASX / AIM announcement – Corporate Update on 24 April 2026
4
See ASX / AIM announcements – Celsius appoints Grant Samuel as Financial Adviser on 9 January 2026 and
Corporate Update on 13 April 2026
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
3
• Strategic equity investors – focused principally on mining companies and investment
groups.
The first phase of the offtake-linked financing stream has completed with a broad range of
Non-Binding Indicative Offers (“NBIO”) received across potential debt and equity
components of a funding package. Shortlisted parties have been invited to participate into
a second phase of the process.
To support increased optionality and competitive tension as well as an optimal cost-
efficient funding solution, the offtake-linked financing stream was augmented with
financing pathways for Philippine and international project finance banks and prospective
strategic equity investors.
The timeline for completion of the MCB Project financing process and a Final Investment
Decision (“FID”) has been extended to Q4 2026. The revised timeline supports the expected
timing required to:
• Finalise the restructuring of MMCI (see update below);
• Complete vendor legal and independent technical expert reports;
• Facilitate detailed due diligence, site visits, management presentations and internal
investment and credit approval processes for all streams; and
• Negotiate and execute transaction documentation.
EPC and FEED-level engineering workstreams are continuing to be progressed in parallel,
with a target FID within this timeframe.
In addition to the broader structured financing process, more immediate funding options
(which do not include a Celsius equity raising) to support early works programmes are also
being considered.
An updated timeline for the MCB Project is set out below.
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
4
The revised project timeline, is predicated on the completion of the funding process and
the commencement of construction within the Quarter 4 of Calendar Year (“CY”) 2026.
Completion of construction and development is expected to take ~2.5 years with
commissioning targeted to start in late 2028 and first concentrate targeted within the first
half of 20295
.
MMCI restructuring
Background
In the Philippines, the holder of a Mineral Production Sharing Agreement (“MPSA”) must have
60% of outstanding shares being owned by a Philippine entity, while a separate mineral
processing company may be up to 100% foreign-owned.
Accordingly, the following ownership arrangements for the MCB Project were agreed via
binding deeds and agreements on 17 March 2023:
• Sodor, Inc. ("Sodor") was to acquire a 60% legal ownership in Makilala Mining Company,
Inc. (“MMCI”) for consideration of PHP 300 million (~US$5 million);
• PMR Holding Corp. (“PMR”), an affiliate of Sodor, was to subscribe for shares in PDEP Inc.
(“PDEP”), the intended mineral processing company for the MCB Project, for an amount
of ~US$38 million (comprising of ~US$43 million less the PHP 300 million subscription in
MMCI by Sodor); and
• These arrangements were to be relinquished, if Sodor and PMR had not provided the
required payment within two years, unless shortened or extended by mutual
agreement.6
The MCB Project was to be owned and operated via the following two entities:
• MMCI - which would hold the MPSA and develop and operate the mine; and
• PDEP - which would own, develop and operate the processing plant and other ancillary
equipment and assets, and would not be subject to foreign ownership restrictions.
Further to the execution of agreements with Sodor and PMR, the expiry date for the payment
of ~US$43 million was extended to 16 February 20267
.
Following the expiry of this deadline, Celsius provided written notice to Sodor that the MMCI
shares must be relinquished in accordance with the agreement.
Notwithstanding the expiry of the payment deadline (and the provision of the notice to
Sodor outlined above), Sodor subsequently (being ~30 days following expiring deadline)
5
See ASX / AIM announcements – MCB Definitive Feasibility Study confirms stronger economics on 23 January
2026 and Corporate Update on 13 April 2026
6
Full details of the agreements and the intended interests of each party’s interests in MMCI and PDEP are set out
in the 20 March 2023 ASX / AIM Announcement – CLA enters Binding Deed with local companies for MCB Project.
7
See 24 February 2025 ASX / AIM Announcement – MCB Project secures funding to jumpstart development; 27
June 2025 ASX / AIM Announcement – FEED and Feasibility Update commence at MCB Project site; and 19 May
2025 ASX / AIM Announcement – MCB Project advances towards Construction.
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
5
attempted to pay the outstanding amount of PHP 300 million (~US$5 million) and a notice
was received from PMR stating that it had sufficient funding to complete its subscription of
shares in PDEP.
Sodor and PMR then initiated an alternative conflict resolution process and sought an
interim order to prevent the sale or transfer of MMCI shares to another party.
On 21 April 2026, the initial conflict resolution process was concluded in Celsius’ favour with
the interim orders sought by Sodor and PMR being denied.
To further protect its interests, Celsius initiated an emergency alternative conflict resolution
process and applied for the following interim orders:
• Prevention of Sodor from exercising any rights as a shareholder or as a director of MMCI;
• Maintenance of the status quo until the determination of a broader conflict resolution
process; and
• In the event of Sodor requisitioning a shareholders meeting, Sodor and any of its
nominees being restricted from implementing any actions or resolutions passed until
the determination of a broader conflict resolution process has been completed.
It is expected that the matter of the application for interim orders will be concluded in May
2026.
Celsius also initiated a broader conflict resolution process focused on enforcing the
relinquishment of the Sodor and PMR arrangements, which would enable it to progress the
transfer of shares in MMCI to a new qualified Filipino partner.
Notwithstanding Celsius’ emergency application to preserve the status quo until the
finalisation of the broader resolution process, and in advance of its completion, the
following actions were subsequently undertaken:
• Mr Julito “Sarge” Sarmiento8
resigned his position as a Makaila Holding Limited (“MHL”)
representative to the MMCI Board as well his position as Chair and President of MMCI on
20 April 2026; and
• Sodor requisitioned a MMCI shareholder’s meeting, which was held on 20 April 2026,
during which a series of resolutions were passed including:
o all five board seats being declared vacant;
o Sodor appointing three representatives to the MMCI Board, including Mr Julito
“Sarge” Sarmiento, who was also re-appointed as Chair and President;
o the preventative suspension of several senior executives; and
o appointment of a new company secretary and several executive officers.
8
Julito “Sarge” Sarmiento resigned from the Celsius Board of Directors on 26 November 2025. See 26 November
2025 ASX / AIM Announcement – Results of Meeting.
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
6
Celsius remains of the view that the right of Sodor and PMR to make payment on the shares
has expired. It intends to continue to preserve its rights and position under the alternative
conflict resolution processes that are presently underway.
The Company also intends to rigorously defend its broader interests, which may include
pursuing legal action against any individuals that are deemed to have breached duties of
fiduciary and/or confidentiality to MMCI.
Way forward
Celsius is in advanced discussions with a new qualified Filipino partner that would acquire
the 60% interest in MMCI previously held by Sodor, which would result in Celsius retaining its
40% direct interest in MMCI.
This could enable Celsius to retain a 100% interest in PDEP and optimise its share of
economics ahead of any potential sell-down or dilution to a new investor as part of the MCB
Project funding process.
An indicative structure for the MCB Project is set out below9
.
Completion of ~A$9.3m equity raising
During the Quarter, Celsius strengthened its cash position through the completion of ~A$9.3
million equity raising.10
The equity offering comprised of:
• Placement shares being issued at A$0.02 per share; and
9
Subject to applicable Philippine legal requirements.
10
See 23 February 2026 ASX / AIM Announcement – Celsius raises A$9.3m in strong institutional placement.
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
7
• 1 free attaching option for every 2 placement shares issued, expiring 3 years from the
date of issue and with an exercise price of A$0.035 per option.
A total of 463,250,000 placement shares were issued to raise A$9.265 million. The issuance
of a further 1,750,000 placement shares to participating Celsius Directors remains subject
to shareholder approval.11
The issuance of 231,625,000 placement options to unrelated parties and 875,000 placement
options to participating Celsius Directors also remains subject to approval.
Celsius also announced its intention, following the completion of the placement, to make a
pro-rata non-renounceable offer to all eligible shareholders for 1 option for every 10 shares
held by eligible investors on a yet-to-be-set record date, on the same terms as the
placement options.
Key uses of proceeds include:
• General working capital;
• Advisory costs associated with the MCB Project financing process;
• Ongoing compliance activities for the MCB, Sagay and Botilao projects,
• Further exploration at the Botilao Project; and
• Placement transaction costs.
Potential assignment of MIC loan
During the Quarter, MMCI applied for the final drawdown of funds of ~US$0.9 million under
its First Omnibus Loan and Security Agreement (“First OLSA”) with the Philippine sovereign
wealth fund, Maharlika Investment Corporation (MIC).12
MIC has undertaken to process this
request subject to a technical review of the Definitive Feasibility Study using an independent
technical expert.
The total drawdown under the First OLSA is US$9.1 million, with ~US$0.9 million remaining
undrawn under the US$10 million facility.
Subsequent to the Quarter, MIC issued a press release with respect to the execution of an
assignment agreement for the sale and assignment of its loan position under the OLSA with
to Equinaire Holdings Limited, a wholly owned subsidiary of Kiri Industries Limited (“Kiri”) of
India.
Celsius was not informed of MIC’s intentions to progress a sale and assignment of the OLSA
to Kiri and was not provided a copy of the press release ahead of its announcement.
Formal notice was received by MMCI on 28 April 2026.
11
A General Meeting is scheduled for 30 April 2026. For further details see 1 April 2026 ASX / AIM Announcement -
Notice of General Meeting / Proxy Form, and 16 April 2026 ASX / AIM Announcement – Addendum to Notice of
General Meeting.
12
See 24 February 2025 ASX/AIM Announcement – MCB Project secures funding to jumpstart development.
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
8
The Company is assessing its position and is taking advice from its legal and financial
advisers13
.
DFS confirms a technically and economically enhanced MCB Project
In January 2026, a Definitive Feasibility Study (“DFS”) was released the MCB Project.14
The DFS confirmed a technically and economically enhanced MCB Project. It was
completed to a Class 3 level of estimate accuracy (typically up to ±15%), consistent with
industry standards and suitable for project financing and execution planning. The DFS
follows a Scoping Study announced in December 2021.15
Key technical and financial DFS outcomes are set out in the table below.
Item 1st 10 years Life of mine
Ore Mined 24.5 MT 89.7 MT
Copper Grade 1.08% 0.69%
Gold Grade 0.51 g/t 0.24 g/t
Copper Recovery 92.5% 89.7%
Gold Recovery 79.7% 72.6%
Mine Life 10 Years 35.3 Years
Process Plant Throughput 2.64 MTPA 2.64 MTPA
Average Annual Cu Concentrate Production
(dry) 102.5 kt 66.0 kt
Total Copper Recovered 542 Mlbs 1,234 Mlbs
Total Gold Recovered 319 koz 507 koz
Copper Price for 1st
9 Years (assumed) US$4.3/lb US$4.3/lb
Copper Price for Remaining Years US$7.0/lb US$7.0/lb
Gold Price for 1st 9 Years (assumed) US$3,000/oz US$3,000/oz
Copper Price for Remaining years US$4,500/lb US$4,500/lb
Initial Capital US$276 M US$276 M
NPV (Post Tax; 8%) US$444 M US$771 M
NPV (Pre Tax; 8%) US$771 M US$1.3 BN
IRR (Pre Tax) 28.5% 30.5%
IRR (Post Tax) 22.1% 24.1%
Payback from Start of Production1
4.7 Years 4.7 Years
LOM C1 Cost (net of by-product credits) US$0.41/lb Cu US$1.73/lb Cu
Continued momentum across key MCB Project workstreams
Following the completion of the MCB Project DFS, the focus has shifted towards planning
around mine development and construction.
13
See 27 April 2026 ASX/AIM Announcement – Potential assignment of MIC OLSA.
14
See 23 January 2026 ASX/AIM Announcement – MCB Definitive Feasibility Study confirms stronger economics.
15
See 1 December 2021 ASX/AIM Announcement – MCB Project Scoping Study.
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
9
Underground mine development
Strategic planning for underground mine development was advanced with an Expression
of Interest issued to mining consultancy firms and individuals to support the development
of a comprehensive scope of works.
Process Plant including Civil Works
A tendering process for an Engineering, Procurement, and Construction (“EPC”) contract for
the Process Plant was initiated with the issuance of tender documents to qualified parties.
An Owner’s Engineer Scope of Works was also formally issued to both Philippine and
international parties, to support technical oversight and quality assurance.
Main Access Road
During the Quarter there was ongoing collaboration with the Kalinga Provincial Engineering
Office with respect to the proposed Main Access Road. Key initiatives included:
• Completion of a site visit to assess the proposed Main Access Road exit;
• Continued progress on the road survey, with completion of ~50% of the topographic
survey and 65% of the overall scope of works; and
• Ongoing data processing and preliminary design activities.
These initiatives are laying the groundwork for the construction phase once funding is in
place.
Power supply and infrastructure
Introductory meetings with hydropower suppliers were conducted to explore potential
alternative sources of sustainable and reliable energy solutions for the MCB Project.
Ongoing commitment to the MCB Project community and local stakeholders
During the Quarter, several strategic social and economic initiatives were implemented to
enhance community capacity and drive sustainable development.
Stakeholder engagement
Two mining Information, Education and Communication (“IEC”) campaigns were
conducted at a local government unit and nearby schools to strengthen stakeholder
awareness and deepen community engagement. These initiatives encouraged active
participation in environmental stewardship and responsible resource management, while
fostering support for the MCB Project. They also highlighted the project’s potential to
generate local employment opportunities and stimulate business growth in surrounding
communities.
In parallel, monitoring and management of communities continued, ensuring that any
matters raised were addressed proactively and constructively. This approach reinforced
trust, maintained positive relationships, and demonstrated the company’s commitment to
sustainable development and stakeholder collaboration.
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
10
Community-based skills training
The third and fourth batches of Financial Literacy Training were completed, with 64
community members (18 males, 46 females) equipped with essential financial
management skills to support household and community economic well-being.
The second batch of TESDA Masonry NC II produced 24 graduates (18 males, 6 females). As
part of their practicum, trainees contributed to enhancing local community facilities. This
initiative not only builds local skills but also creates pathways for livelihood opportunities
while benefitting community infrastructure and services.
Educational assistance and scholarship program
Education support also advanced with the completion of the Balatoc Education
Committee’s validation of the list of scholars for the 2nd Semester of School year 2025-
2026. A total of 207 college students, 30 post-graduate students, and four reviewees were
confirmed, reinforcing the project’s commitment to academic development.
In addition, three community members supported through the initiative successfully
passed the Criminology Licensure Exam, raising the total number of Board Passers since the
program inception to 15.
Health initiatives
Two medical-dental missions were conducted for the period, in partnership with the
Municipal Health Office. A wide range of health services were provided to the host
community which not only addressed immediate health needs but also strengthened
community awareness.
Baseline studies
Data gathering for the Balatoc Cultural Heritage Baseline Study was completed, which
included key informant interviews, focus group discussions, and oral history sessions. These
efforts are vital in documenting and preserving cultural knowledge, practices, and
narratives for future generations.
Infrastructure support
Repairs and construction works were initiated on key community facilities, including a
suspension bridge, a potable water system, and slope stabilisation structures. These
initiatives are vital in ensuring safe access, reliable basic services, and resilient
infrastructure, thereby reinforcing the company’s commitment to sustainable development
and the long-term well-being of host communities.
Land access
The process of clan land boundary delineation for the construction and future operations
of the MCB Project was formally initiated. House-to-house campaigns were actively carried
out to provide clear explanations to community members regarding the process and to
seek endorsement of clan representatives, ensuring transparency and inclusivity. In
parallel, field validation of clan boundaries is underway.
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
11
MCB environmental management and ancillary permits
Environmental protection and enhancement program
The Environmental Management Bureau successfully completed the site validation for the
2nd Semester 2025 Compliance Monitoring Report, ensuring that operational and
environmental commitments were thoroughly assessed and documented in line with
regulatory standards. This validation exercise provided valuable insights into project
performance, confirming compliance with established requirements while highlighting
opportunities for continuous improvement. It further underscores the MCB Project’s
dedication to transparency, accountability, and regulatory adherence as it advances
toward the next phases of implementation.
In collaboration with the Balatoc Barangay Local Government Unit, the project site team
also participated in a community clean-up drive, reinforcing shared responsibility for
environmental stewardship and promoting collective action to maintain a healthier local
environment.
Environmental management system
The company strengthened its Environmental Management System by developing key
policies, standard operating procedures, and forms, including the Environmental
Management Plan, Risk Assessment, Management of Change, and Control of Documented
Information. These initiatives enhance consistency, reinforce compliance, and align
operations with ISO 14001 standards.
Continuous monitoring addressed gaps identified in the Second Party Audit, ensuring
readiness for future reviews. Capacity-building was also prioritised through continued
International Electrotechnical Commission sessions, equipping employees with greater
awareness of their environmental roles and responsibilities.
Ancillary permits
Collaboration with the Community Environment and Natural Resources Office in Tabuk City
progressed steadily to facilitate the Tree Cutting Permit application. A Memorandum of
Agreement (“MOA”) was also signed with Kalinga State University, formally appointing the
institution to lead the propagation of replacement seedlings. Following this partnership, a
Notice to Proceed was issued, officially launching the seedling propagation activities
required to support compliance with the permit conditions.
Engagement with the Local Government Unit of Pasil is ongoing, with discussions on their
counterproposal to the MOA progressing. The primary purpose of the MOA is to streamline
permitting requirements and facilitate efficient project implementation. Actions are
underway to finalise the terms and establish a clear framework for collaboration and
shared responsibilities.
Botilao Copper-Gold Prospect, Philippines
The Botilao exploration permit was renewed during the Quarter, which will enable the
continuation of exploration activities adjacent to the MCB Project.16
The permit renewal
secures the capacity to expand its resource base and demonstrates ongoing regulatory
support from Philippine authorities. It also further strengthens Celsius’ portfolio in Northern
16
See 5 February 2026 ASX/AIM Announcement – Philippine Government approves renewal of Botilao Permit.
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
12
Luzon and provides the potential for future discoveries that could complement the MCB
Project.
Sagay Copper-Gold Project, Philippines
Tambuli Mining Company, Inc. (“TMCI”), a wholly owned Philippine subsidiary of Celsius in
the Negros Islands, continues to coordinate closely with the DENR’s Environmental
Management Bureau to advance the approval of its Environmental Impact Statement
(“EIS”) for the Sagay Copper-Gold Project.
The EIS is a prerequisite for securing an Environmental Compliance Certificate ("ECC”). Once
granted, the ECC will mark a critical key milestone, validating that the Sagay Project
development plans and engineering designs are technically sound, environmentally
sustainable, and socially acceptable. It will also enable TMCI to move forward with its
application for a Declaration of Mining Project Feasibility, which would support a Mining
Permit.17
Opuwo Cobalt Project, Namibia
A sales process for the non-core Opuwo Project in Namibia is progressing well with multiple
parties submitting NBIO’s and completing site visits.
Celsius remains hopeful of completing a sale before the end of Calendar Year 2026.
During the Quarter, Celsius completed its de-listing from the Namibia Securities Exchange
with all former shareholders transferring their holdings to the ASX.
Cullarin West Project, NSW
The relinquishment of this project was effected in February 2026. No work on the project
was conducted during the Quarter and reporting on it will cease from now.
17
See 8 January 2024 ASX/AIM Announcement – Celsius’ Sagay Project applies for DMPF.
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
13
Cash position
At the end of the quarter, the Company held approximately A$9.836 million in cash reserves,
of which A$929k was held in MMCI.
ASX additional information
The Company provides the following information pursuant to ASX Listing Rule requirements:
• ASX Listing Rule 5.3.1:
Approximately A$1.55 million was spent on exploration expenditure during the quarter,
primarily relating to the development of the MCB and Sagay Projects.
• ASX Listing Rule 5.3.2:
Nil was spent on mine production and development activities during the quarter.
• ASX Listing Rule 5.3.5:
The Company advises that there were approximately A$414k in payments made to
related parties of the Company and their associates during the Quarter for Director and
consultancy fees, of which A$312k was paid by MMCI using funds advanced from MIC.
Tenement Table: ASX Listing Rule 5.3.3 - mining tenement interests held at the end of
the quarter and their location
Permit
name
Permit
number
Registered
holder /
applicant
Permit
status
Permit
expiry
Interest /
contractual right
New South Wales
Cullarin West EL 8996
Cullarin Metals
Pty Ltd
Relinquished 17/08/2026 100%
Namibia
Opuwo EL 4346
Gecko Cobalt
Holdings
Awaiting
issuance of
tenement permit
TBA 95%
Philippines
Maalinao-
Caigutan-
Biyog
MPSA-356-
2024-CAR
Makilala Mining
Company Inc.
Granted 13/03/2049 40%
Botilao
EP-011-2023-
CAR
Makilala Mining
Company Inc.
Granted 27/01/2028 40%
Panaon
EXPA-000127-
VIII
PDEP, Inc.
Complying with
further
requirements
TBA 100%
Sagay EP-000003-VI
Tambuli Mining
Company Inc.
Granted
Automatic
extension
until the
approval of
the
DMPF/MPSA
100%
ASX RELEASE | QUARTERLY REPORT | 31 March 2026
14
Key information on the mining tenements:
• Mining tenement interests acquired or disposed of during the Quarter and their
location: Cullarin West permit EL 8996 in New South Wales was relinquished in
February 2026;
• Beneficial percentage interests held in farm-in or farm-out agreements at the end of
the Quarter: not applicable; and
• Beneficial percentage interests in farm-in or farm-out agreements acquired or
disposed of during the Quarter: nil.
This announcement has been authorised by the Board of Directors of Celsius Resources
Limited.
The information contained within this announcement is deemed by the Company to
constitute inside information as stipulated under the Market Abuse Regulations (EU) No.
596/2014 as it forms part of UK Domestic Law by virtue of the European Union (Withdrawal)
Act 2018.
For further information contact: