Corporate Presentation
Released
Released
Announcement PDF
Multi-asset and
near-term, lowcost copper
producer
Corporate Presentation
September 2024
ASX/AIM: CLA
DISCLAIMER & NOTES
This presentation has been prepared by Celsius Resources Limited ("Celsius" or "CLA"). The
information contained in this presentation is a professional opinion only and is given in good
faith.
All reasonable care has been taken to ensure that the facts stated in these presentation materials
are accurate and that any forecasts, opinions and expectations contained therein are fair and
reasonable. Accordingly, no representation or warranty express or implied is made to the
fairness, accuracy, completeness or correctness of these materials or opinions contained therein
and each receipt of these presentation materials must make its own investigation and
assessment of the matters contained therein. In particular, but without prejudice to the generality
of the foregoing, no representation or warranty is given, and no responsibility or liability is
accepted by the Company or any of its representatives, as to the achievement or reasonableness
of any future projections or the assumption underlying them, or any forecasts, estimates, or
statements as to prospects contained or referred to in these presentation materials.
No responsibility or liability whatsoever is accepted by the Company or any of its representatives
for any loss howsoever arising from any use of, or reliance upon, or in connection with, these
presentation materials or their contents or otherwise arising in connection therewith. In issuing
these presentation materials, the Company does not undertake any obligation to update or to
correct any inaccuracies which may become apparent in these presentation materials. These
presentation materials are being supplied for you for your own information and may not be
distributed, published, reproduced or otherwise made available to any other person with
addresses in Canada, Australia, Japan, the Republic of Ireland, or the United States, its territories
or possessions or in any other country outside the United Kingdom where such distribution or
availability may lead to a breach of any law or regulatory requirements.
In the United Kingdom, these presentation materials have not been approved by an authorised
person pursuant to section 21 of the Financial Services and Markets Act 2000 (the "FSMA") and,
accordingly, these presentation materials are only directed at persons in the United Kingdom
who fall within the exemptions contained in Articles 19 and 49 of the Financial Services and
Markets Act 2000 (Financial Promotion) Order 2005 (such as persons who are authorised or
exempt persons within the meaning of the FSMA and certain other investment professionals,
high net worth companies, unincorporated associations or partnerships and the trustees of high
value trusts) and persons who are otherwise permitted by law to receive them. These
presentation materials are directed only at persons having professional experience in matters
relating to investments and any investment or investment activity to which these presentation
materials relate and is only available to such persons. Persons of any other description, including
those who do not have professional experience in matters relating to investments, should not
rely on these presentation materials or act upon their content. These presentation materials have
not been approved by the Financial Conduct Authority (the "FCA") as a prospectus for the
purposes of section 87A of the FSMA and have not been filed with the FCA pursuant to the
United Kingdom Prospectus Rules.
The distribution of these presentation materials in other jurisdictions may be restricted by
law, and persons into whose possession these presentation materials come should inform
themselves about, and observe, any such restrictions. Any failure to comply with these
restrictions may constitute a violation of the laws of the relevant jurisdiction.
All amounts in AUD unless stated otherwise.
The information in this presentation with respect to the updated JORC compliant Mineral
Resource estimate (MRE) for the MCB Project was announced by Celsius to the ASX on 12
December 2022. Celsius confirms that it is not aware of any new information or data that
materially affects the information included in the announcement dated 12 December 2022
and that all material assumptions and technical parameters underpinning the Mineral
Resource Estimate continue to apply and have not materially changed.
The information in this announcement with respect to the outcomes of the Study for the
MCB Project was first released by Celsius to ASX on 1 December 2021. Celsius confirms that
all material assumptions underpinning the production target and forecast financial
information derived from the production target referred to in the announcement of 1
December 2021 continue to apply and have not materially changed.
The information in this presentation with respect to the Mineral Resource estimate for the
Sagay Project was first announced by Celsius to the ASX on 7 November 2022. An updated
resource was announced to the ASX/AIM on 06 February 2024 and Celsius confirms that it is
not aware of any new information or data that materially affects the information included in
the announcement and that all material assumptions and technical parameters
underpinning the Mineral Resource estimate continue to apply and have not materially
changed.
The information is this presentation with respect to the Mineral Resource estimate for the
Opuwo Project was first announced by Celsius to ASX on 1 July 2021. Celsius confirms that
it is not aware of any new information or data that materially affects the information included
in the announcement dated 1 July 2021 and that all material assumptions and technical
parameters underpinning the Mineral Resource estimate continue to apply and have not
materially changed.
2
CELSIUS RESOURCES (CLA) | Investment Portfolio
▪ CLA is a dual listed (ASX/AIM)
resources company with
copper/gold projects in the
Philippines.
▪ A multi-asset company with
copper/gold JORC resources in
the Philippines of 650Mt.
▪ World-class porphyry projects with
geographic diversity within the
Philippines.
▪ Multi-generational — more than a
lifetime of contained copper and
gold to be mined.
Refer to ASX announcements dated 1 July 2021, 12 December 2022, 7 August 2023, 01 January 2024, 02 February 2024, and 18 Marc h 2024.
3
Philippines | Open for Business
Celsius has received:
▪ the first mining permit (MPSA) for a new copper mine in 15 years; and
▪ the first FPIC Certification Precondition for a copper/gold project in 5 years
Refer to ASX/AIM announcements dated 18 March 2024 and 4 September 2024
▪
Strong government support for responsible
mining in the Philippines
▪
Clear processes for permitting
▪
Clear processes for community participation
▪
Solid contributions to indigenous
communities
▪
Strong legal protection for the life of permit
4
CELSIUS RESOURCES |
Commitment to Leading ESG Practices
Celsius Resources is committed to the sustainable discovery and development of copper and gold. The
Company defines sustainability as the purposeful delivery of all projects in a manner that is environmentally
responsible while simultaneously contributing to the long-term socio-economic development of our host
communities.
5
CELSIUS RESOURCES |
Highly Experienced Board and Management
JULITO SARMIENTO
Executive Chairman
An experienced Philippine lawyer with over
30 years specialising in mining, environment,
social license, indigenous peoples,
renewable energy, government relations
and who has established close relationships
with civil society, Church and local
communities.
MARK VAN KERKWIJK
Executive Director
Mark brings a strategic and entrepreneurial
approach to executing CLA’s flagship
projects. His extensive experience as a
substantial private investor in the resource
sector, particularly in the mining industry,
has equipped him with a deep knowledge
and understanding of market dynamics,
shareholders’ interests and investment
strategies that drive company growth and
innovation.
PETER HUME
Non-Executive Director
Over 40 years’ experience on major mining and
construction development projects on lead roles
throughout Australia, Philippines and
internationally. With demonstrated experience in
general management, project management,
construction management, dispute resolution,
infrastructure, and process design, concept
planning to commissioning and operations, as
well as design management, development, and
implementation of quality, safety, and
maintenance management systems.
PAUL DUDLEY
Non-Executive Director
KELLIE DAVIS
Corporate Secretary
ATTILENORE MANERO
Non-Executive Sustainability Director
Corporate Affairs & Sustainability DirectorPhilippines
A development professional specialising in
social and environmental impacts management,
with more than 13 years of substantial practical
experience in managing a diverse team of local
and international experts whilst carrying out
studies leading to the development and
implementation of social and environmental
plans and programs consistent with local
statutes and internationally accepted standards.
A Fellow of the Institute of Chartered
Accountants of England and Wales
and a Member of the UK's Chartered
Institute of Securities and
Investments. He founded Aer
Ventures (formerly HD Capital) in
2011 where he is Managing Partner,
advising and leading corporate
transactions on numerous public
and private companies.
Over 20 years of experience in
accounting and secretarial ASX
Compliance, predominantly in the
exploration and resources sector
beginning her career in Audit with Ernst
and Young.
PATRIQUE JANE DURAN
Chief Operations Officer- Philippines
A mining engineer, formerly with
the Philippine Mines and
Geosciences Bureau, with ten years
experience in various lead roles in
government and private sectors in
the mining industry.
6
MCB Copper-Gold Project
Kalinga, Philippines
7
MMCI | MCB Copper-Gold Project
Key Features
• Celsius’ flagship project held by its Philippine
subsidiary, Makilala Mining Company, Inc.
• Located 320km north of Manila.
• Tenement covers c.2,500 hectares.
• Mining Permit issued on 15 March 2024 which grants
the Company exclusive rights to undertake rational
exploration, development, and commercial
production of copper and associated minerals for a
period of 25 years, renewable for another 25 years.
Geology & Mineralisation
• The MCB deposit comprises classic porphyry style
copper-gold mineralisation with a high-grade sub
vertical core, representing approximately 28% of the
total Mineral Resource Estimate.
• 55 diamond drill holes completed from 2006-
2022 with a cumulative drilling distance of 30,122m
at a total cost of A$30.9M.
Refer to ASX announcements dated 01 December 2021,12 December 2022, and 18 March 2024
8
MCB | Outstanding Assay Results
Highlights
•
Intersection of 611.4m @ 1.39% copper and 0.75
g/t gold from 32.5m (1.67% CuEq*).
•
Multiple internal higher-grade results confirmed:
o 150.85m @ 1.90% copper and 1.57 g/t
gold from 207./15m (2.55% CuEq*)
o 234.45m @ 1.90% copper and 0.87 g/t
gold from 391.55m (2.22% CuEq*), and
o 77.55m @ 2.47% copper and 2.12 g/t gold
from 232.10m (3.34% CuEq*)
Near surface high-grade copper including:
o 10.5m @ 0.69% copper and 0.07g/t gold
from 19.5m
o 65m @ 1.73% copper and 0.37g/t gold
from 66m
•
* The reporting of copper equivalent values (CuEq) was based on long term predicted copper prices of US$4.0lb, gold price of US$1,695/oz, and with copper
and gold recoveries of 94.2% and 79%, respectively as defined in the reported study for the MCB Project. (See ASX announcemen t on 1 December 2021).
Assumed copper and gold price predictions will vary with market conditions and this will be re -evaluated in future studies.
Refer to ASX announcement dated 4 July and 19 October 2022
9
MCB | Mineral Resource Estimate
An updated JORC Mineral Resource Estimate was
announced in December 2022, comprising:
Section 1 with the interpreted host rock geology relative to
the defined copper mineralised domains.
▪
Global Mineral Resource of 338Mt @ 0.47% copper and
0.12g/t gold (0.2% Cu cut-off).
▪
Total Resource includes approximately 1.6Mt of
contained copper and approx. 1.3Moz of gold.
Note: Estimates have been rounded to the nearest MT of ore, two significant figures for Cu and Au grade,
and to the nearest kt of Cu metal and kozs of Au metal. Some errors may occur due to rounding.
Refer to the ASX announcement dated 12 December 2022 for the Updated JORC Mineral Resource Statement prepared by Steve Olsen (MAusIMM, AIG)
10
MCB | High Grades & Recoveries and Solid Economics
Key Inputs
▪
▪
Item
Preferred Case
First 10 Years
Preferred Case
Life of Mine (25
Years)
Optimised mine plan focused on the high-grade
Cu-Au portion of the MRE, equating to 49 Mt at
0.85% Cu and 0.41g/t Au, 100% of which was
classified as Indicated Resource
Ore Mined
22.2 Mt
48.8 Mt
Copper Grade
1.14%
0.85%
Copper Recovery
94.2%
94.2%
High marketability of copper concentrate
Gold Grade
0.54 g/t
0.41 g/t
Gold Recovery
79.0%
79.0%
Process Plant Throughput
2.28 Mtpa
2.28 Mtpa
Average Annual Copper
Production (Payable)
22ktpa
16 ktpa
Average Annual Gold
Production (Payable)
27 kozpa
19 kozpa
Initial Capital
USD 253M
USD 253M
N/A
USD464M
-
31%
After-Tax NPV8%
Internal Rate of Return
Payback
C1 Cost (net of gold credits)
2.67 years
USD 0.73/lb Cu
USD 1.29/lb Cu
*Assumption: Cu = USD4.0/lb; Au = USD 1,695/oz
Refer to ASX announcement on the Positive Scoping Study dated 1 December 2021
11
MCB Project | Permitting and Approvals
Refer to ASX Announcements dated 4 October 2022, 15 November 2022, 31 May 2023, 29 September 2023, 18 March 2024, and 04 Sept ember 2024
12
MCB Project | Offsite Infrastructure
The MCB Project’s mine plan is meticulously outlined to establish supportive infrastructure essential for sustaining and
managing its operations seamlessly, from production to the delivery of concentrates.
Site Infrastructure
Power Supply
Site Water Management
▪ The MCB Project will comprise an
▪ The Project’s 12-megawatt power demand
▪ A freshwater dam and the underground
underground mine and surface infrastructures.
▪ The site layout includes a process plant,
ancillary facilities, and a general admin facility.
▪ Concentrates will be transported from the
plant site to the port facility by trucks using
lined containers, via the 21-km main access
road that is to be constructed.
▪ The containers will be stored in a laydown
area near the port and delivered to the
docking area once a vessel is available.
▪ Road alignment from mine site to port will be
jointly developed by MMCI and the Provincial
Local Government Unit.
Refer to ASX Announcement dated 01 December 2021
will be sourced from the nearest substation
of the National Grid Corporation of the
Philippines at San Esteban, Ilocos Sur.
▪ Although existing power lines are
available, it is expected that additional
towers and overhead transmission lines will
be necessary to cater operations.
▪ Alternative power sources may be tapped
in the future when various renewable
energy projects near the area become
operational, including a geothermal power
project and two other hydropower
projects.
water collection pond with estimated
capacity of approximately 100,000m3
and 500,000m3, respectively, will be
constructed to support site operations.
▪ A water treatment plant will be installed
after the collection dam to remove the
impurities from the contact water before
discharging to the nearby river.
▪ The operation will use minimal fresh
water with an average demand of
0.02m3/s, most of which will be
recycled.
13
Sagay Copper Project
Negros Occidental, Philippines
14
TMCI | Sagay Copper Project
▪ Sagay Copper Project is held by Tambuli Mining
Company, Inc. (TMCI), a Philippine subsidiary of
Celsius Resources, Ltd. with a tenement area of
~1,780 hectares.
▪ Exploration commenced in 2008, including:
o geological mapping
o gridlines preparations
o soil and rock sampling
o geophysical surveys consisting of induced
polarisation, resistivity, and ground
magnetics.
▪ A total of 47 drill holes completed from 2012 to
2023 with a cumulative drilling distance of
28,252.20m and a total cost of ~AUD$14.7M.
▪ The culmination of the exploration activities led to
the discovery of a large-scale deep porphyry
copper-gold mineralisation with a shallow,
secondary supergene deposit west of the main
porphyry deposit, which would be the first target
to be developed.
Refer to ASX Announcement dated 20 April 2021 and 06 February 2024
15
Sagay | Updated Mineral Resource
▪ The updated JORC-compliant Mineral Resource Estimate (MRE) is
defined by 45 diamond drill holes which are broadly spaced and
have shown copper mineralisation over an extended area from the
surface down to 1.2 km in depth.
▪ Focus of the update related to the shallow supergene copper
mineralisation which now includes Measured and Indicated Mineral
Resources.
▪ Combined Measured, Indicated and Inferred Mineral Resource of
312 million tonnes @ 0.39% copper and 0.11g/t gold. The Global
Resource remains unchanged with ~1.2 million tonnes of contained
copper and ~1 million ounces of contained gold.
▪ Copper mineralisation is open in multiple directions, with further
shallow targets untested.
▪ Mineralisation exists from near surface down to over 1.2km depth
with strike lengths up to 1 km and true widths extending into the
100’s of metres.
▪ The shallow copper zone offers Celsius the opportunity to develop a
low-cost start-up opportunity which was the basis of the feasibility
study that was submitted to the Philippine Government.
Refer to ASX/AIM Announcement dated 06 February 2024
16
Sagay | Low-cost, near-term project
▪
▪
▪
As a requirement of the Philippine Government, a Mining ▪
Project Feasibility Study was conducted to evaluate the
technical and financial viability of the shallow supergene
chalcocite deposit and advance the project towards
▪
project development and operations.
The study confirmed the presence of minerals in the area
which are recoverable by processing the ore through
gravity separation which was determined to be
economically sound while ensuring that environmental
protection and preservation methods would be
▪
implemented through advanced mining technologies.
Technical, environmental, and social considerations were
incorporated in the mine design to reduce the mine
footprint to approximately 20 hectares.
Refer to ASX/AIM Announcement dated 06 February 2024
The process plant will employ a gravity
concentration method to extract the copper
concentrate from the ore.
Metallurgical test works indicated that the tails
produced is non-acid generating. All tailings will
be managed through dry stacking method which
eliminates the need for tailings dam, thus
removing the possibility of environmental impacts
(tailings spill).
Other alternative disposal methods are being
studied which are currently being implemented
within Southeast Asia and globally.
17
Sagay | Permitting
▪ An application for Declaration of Mining Project Feasibility
(DMPF) was submitted to the Philippine Government in
December 2023, along with the following key documents:
o
o
o
o
o
o
o
Mining Project Feasibility Study
Final Exploration Report
Environmental Impact Statement Report
Environmental Protection and Enhancement Program
Final Mine Rehabilitation and/or Decommissioning Plan
Social Development and Management Program
Care and Maintenance Program
▪ The company is currently finalising an Environmental Impact
Assessment as part of the permitting process to demonstrate
to stakeholders that adequate mitigating measures can be
implemented using best practices, engineering methods,
and advanced technologies, underscoring the company's
commitment to environmental protection and preservation.
▪ The approval of the DMPF and the Environmental
Compliance Certificate (ECC) will trigger the next stage of
the permitting process leading to a mining permit that would
enable the development and operations of the Sagay Project.
Refer to ASX/AIM Announcement dated 08 January 2024
18
Botilao Copper-Gold Prospect
Kalinga, Philippines
19
MMCI | Botilao Copper-Gold Prospect
▪ Located in the Cordillera Administrative Region in the
Philippines, ~320km north of Manila.
▪ It is a prospect within the Makilala portfolio with an
approximate area of 947 hectares, southwest of the MCB
Project.
▪ Exploration permit was issued on 29 September 2023 along
with an approved Exploration and Environmental Work
Program.
▪ Drilling was previously conducted by Lepanto
Exploration Asia in the '70s which determined the
presence of copper-gold mineralisation in the area with
copper grades up to ~1%.
Refer to ASX/AIM Announcement dated 20 June and 07 August 2023
20
Botilao | Initial Exploration Works
▪ The initial two-year exploration program aims to define the extent and
distribution of the observed mineralisation along Botilao Creek.
▪ Exploration activities will consist of regional to semi-detailed
geochemical sampling and mapping to generate future targets for
possible geophysical surveys and eventual diamond drilling activities.
▪ Mapping of different rock types or lithologies in the area will be
conducted to characterise and delineate mineralised or altered zones.
▪ Detailed mapping will focus on identified mineralised outcrops to
ensure proper understanding of the classification and controls of
mineralisation during exploration phase.
Refer to ASX/AIM Announcement dated 20 June and 07 August 2023
21
Botilao | Exploration Upside
With the close spatial relationship and the
similarity of mineralisation style of the MCB and
the Dickson ore bodies, it can be deduced that
both, including the Maalinao Deposit in
between, are part of one porphyry
mineralisation zone.
Long cross section of the MCB Deposit with respect to the Maalinao-Dickson
ore bodies
Panoramic view of the surface projections of the Mt. Mines deposit (MCB) and the Maalinao-Dickson Deposits
Refer to ASX/AIM Announcement dated 20 June and 07 August 2023
22
Celsius | Investment Summary
MCB
Copper-Gold Project
▪ Initial CAPEX of US253m and
payback period of 2.67 years
▪ Potential for 25-year mine life
▪ Mining Permit recently issued
for a period of 25 years,
renewable for 25 years
▪ Extensive funding interest
▪ Huge potential for extending
mine life through adjacent
tenement which is currently
being explored
Sagay Copper Project
Botilao Copper-Gold
Prospect
▪ Combined Measured,
Indicated and Inferred MRE
of 312Mt @ 0.39%Cu and
0.11g/tAu
▪ Clean copper concentrate
▪ Estimated copper grades
of up to ~1% based on
historical drilling
▪ Planning drill campaign
in order to define MRE
▪ Opportunity to develop
low-cost, near-term
sustainable approach
▪ DMPF application submitted
✓
A compelling portfolio of copper projects that offer the potential to generate near-term revenues that could provide the
platform to develop long-lived mining assets.
✓
Positioned to benefit from the next copper boom with near-term, low-cost revenue potential paired with growing copper
demand
✓
Highly experienced Board and Management team with in-country project development experience and demonstrated
capital funding.
Refer to ASX Announcements dated 1 December 2021, 8 January 2024 and 6 February 2024
23
Competent Persons Statement
Information in this presentation relating to the reporting of Mineral Resource Estimates and Exploration Results for
the MCB and Sagay Projects is based on information compiled, reviewed and assessed by Mr. Steven Olsen, who is
a Member of the Australasian Institute of Mining and Metallurgy and the Australian Institute of Geoscientists. Mr.
Olsen is a consultant to Celsius Resources and has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a
Competent Person as defined by the 2012 Edition of the Australasian Code for reporting of Exploration Results,
Mineral Resources and Ore Reserves. Mr. Olsen consents to the inclusion of the data in the form and context in
which it appears.
Information in this report relating to Exploration Results for the Opuwo project is based on information reviewed
and compiled by Dr Rainer Ellmies, who is a Member of the Australasian Institute of Mining and Metallurgy and the
Principal Geological Advisor for the Opuwo Project of Celsius Resources. Mr. Ellmies discovered the Opuwo
deposit in 2012 and has sufficient experience which is relevant to the style of mineralisation and type of deposit
under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined by the
2012 edition of the “Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves”
(the JORC Code). Mr. Ellmies consents to the inclusion of the data in the form and context in which it appears.
24
Level 5, 191 St. Georges Terrace
Perth WA 6000
PO Box 7059
Cloisters Square PO
Perth WA 6850
P: +61 8 9324 4516
W: celsiusresources.com
Australia:
Philippines:
mark@celsiusresources.com.au
peter.hume@celsiusresources.com.au
United Kingdom:
paul.dudley@celsiusresources.com.au
25