Celsius Resources Limited (“Celsius” or the “Company”) (ASX, AIM: CLA) continued its focus on
the Maalinao-Caigutan-Biyog Copper-Gold Project (“MCB Project”) during the September 2026
Quarter (“Quarter”) with the following recent milestones and events occurring:
Progressing towards the completion of the Opuwo transaction
During the Quarter, Celsius continued to progress a sale of its 95% interest in the Opuwo Project
in Namibia to Chinalco (Xiong’an) Mining Corporation Limited, a subsidiary of Aluminum
Corporation of China (“Chinalco”).1
The transaction entails the sale (via its wholly owned subsidiary Opuwo Cobalt Pty Ltd) of an
intercompany loan and Celsius’ 95% interest in Opuwo Cobalt Holdings (Proprietary) Limited
(“Opuwo Cobalt Holdings”) for total cash consideration of US$15 million.
Since the announcement of the transaction on 30 June 2026, the following conditions precedent
have been satisfied:
• Celsius shareholder approval (required under Rule 15 of the AIM Rules for Companies);
• Waiver of pre-emptive rights held by the 5% minority shareholder of Opuwo Cobalt Holdings;
• Renewal of the Environmental Clearance Certificate; and
• Renewal of the Exclusive Prospecting Licence.
Remaining transaction conditions precedent include:
1
For further details on the transaction, see 30 June 2026 ASX / AIM Announcement – Chinalco Mining to acquire
Opuwo Project from Celsius for US$15 million.
• Advancing the sale of the Opuwo Project to Chinalco for US$15 million
• Celsius’ defending its interests in the MCB Project with respect to disputes with Sodor
and Kiri Industries
• Filing of a criminal complaint and disbarment application against Attorney
Sarmiento
• Filing of a criminal complaint against Erika Chalmers
• Filing a complaint against MMCI with the SEC
• Adoption of a new constitution and cancellation of the previously proposed share
consolidation
• Continued progress across key MCB Project workstreams
• Advancing the environmental permitting process for the Sagay Copper-Gold Project
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
2
• Approval by the Namibian Competition Commission and Bank of Namibia (in relation to
exchange controls);
• Clearance by the Chinese National Development and Reform Commission, Ministry of
Commerce and Bureau of Foreign Exchange Administration;
• Warranties remaining true and correct; and
• No material adverse effect.
The completion of the divestment of the Opuwo Project will enable Celsius to increase its focus
on its Philippine portfolio of copper-gold projects and provide a material source of near-term
funding.
Dispute with Sodor
Background
In the Philippines, the holder of a Mineral Production Sharing Agreement (“MPSA”) must be 60%
owned by a Philippine entity, while a separate mineral processing company may be up to 100%
foreign-owned.
To ensure compliance with these requirements, the following ownership arrangements for the
MCB Project were agreed via binding deeds and agreements on 17 March 2023:
• Sodor, Inc. ("Sodor") was to acquire a 60% legal ownership in Makilala Mining Company, Inc.
(“MMCI”) for consideration of PHP 300 million (~US$5 million);
• PMR Holding Corp. (“PMR”), an affiliate of Sodor, was to subscribe for shares in PDEP Inc.
(“PDEP”), the intended mineral processing company for the MCB Project, for an amount of
~US$38 million (comprising of ~US$43 million less the PHP 300 million subscription in MMCI by
Sodor); and
• These arrangements were to be relinquished, if Sodor and PMR had not provided the required
payment within two years, unless shortened or extended by mutual agreement.2
The MCB Project was to be owned and operated via the following two entities:
• MMCI - which would hold the MPSA and develop and operate the mine; and
• PDEP - which would own, develop and operate the processing plant and other ancillary
equipment and assets, and would not be subject to foreign ownership restrictions.
Upon completion of the payment of the ~US$43 million, Sodor and PMR were to hold a combined
30% share of economics in the MCB Project with Celsius retaining a 70% share of economics.
The expiry date for the payment of ~US$43 million was extended to 16 February 2026.3
Following the expiry of this deadline, Celsius provided written notice to Sodor that the MMCI
shares must be relinquished in accordance with the agreement.
Notwithstanding the expiry of the payment deadline (and the provision of the notice to Sodor
outlined above), Sodor subsequently (approximately 30 days after the deadline expired)
attempted to pay the outstanding amount of PHP 300 million (~US$5 million) and a notice was
2
Full details of the agreements and the intended interests of each party’s interests in MMCI and PDEP are set out in
the 20 March 2023 ASX / AIM Announcement – CLA enters Binding Deed with local companies for MCB Project.
3
See 27 June 2025 ASX / AIM Announcement – FEED and Feasibility Update commence at MCB Project site.
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
3
received from PMR stating that it had sufficient funding to complete its subscription of shares in
PDEP.
Arbitration
Celsius believes that the right of Sodor and PMR to make payment has expired.
The dispute has been referred to arbitration, and the arbitrator has set 12 July 2027 as the target
date for an arbitral decision and the award of any damages.4
MMCI stockholders meeting
The MMCI Board, chaired by Attorney Julito “Sarge” Sarmiento, called a Special Stockholders
Meeting in August 2026. At the meeting it was proposed to increase the authorised capital stock
of MMCI by PHP6 billion (~A$138.5 million). MMCI extended an invitation to Equinaire Holdings
Limited (“Equinaire”) to attend the meeting.5
Celsius requested that Equinaire’s representatives be excluded from the meeting. However,
Attorney Sarmiento, who presided over the meeting, overruled these objections.
Under the Philippine Revised Corporation Code, an increase in its capital stock requires the
approval of two-thirds of stockholders. This typically would have allowed MHL to use its voting
rights over its 40% interest in MMCI to block the resolution.
However, Attorney Sarmiento, determined that MHL was unable to vote and that Equinaire held
a power of attorney over its 40% shareholding in MMCI.
Accordingly, with the support of Equinaire, the resolution to expand the authorised capital stock
of MMCI was approved at the meeting.
Subsequent to the meeting, Celsius successfully sought an interim arbitration order:
• Preventing any action that would increase MMCI’s authorised capital stock; and
• Pending further arbitration orders, directing MMCI to maintain the existing capital and
ownership structure of MMCI and to refrain from any action that would alter such
structure.
Consignation case
Notwithstanding the expiry referenced above and the instigation of arbitration, Sodor deposited
PHP300 million with the Office of the Clerk of Court and filed a consignation application with the
Regional Trial Court in Mariveles, Bataan (“RTC Bataan”), seeking an order for MHL to accept the
payment of PHP300 million by Sodor for a 60% interest in MMCI.6
During the Quarter, MHL applied for a Motion to Refer the Case to Arbitration, whereby it sought
to suspend the consignation proceedings until the conclusion of arbitration between the parties.
The RTC Bataan declined MHL’s motion on the basis that consignation was a matter that could
only be decided by the court and not arbitration. However, it acknowledged that the arbitration
process could continue and decide the parties’ contractual claims and remedies.
4
See 23 October 2026 ASX / AIM Announcement – Corporate update.
5
See 17 August 2026 ASX / AIM Announcement – Corporate update.
6
See 27 August 2026 ASX / AIM Announcement – Corporate update.
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
4
A Motion for Reconsideration, which was filed by MHL with the RTC Bataan, was subsequently
dismissed. MHL has filed a petition with the Court of Appeals and if necessary, intends to appeal
to the Supreme Court of the Philippines.
Dispute with Equinaire
Background
In June 2026, Maharlika Investment Corporation (“MIC”) purportedly sold and assigned its rights
and interests under an Omnibus Loan and Security Agreement (“OLSA”) with MMCI to Equinaire,
a wholly owned subsidiary of Kiri Industries Limited (“Kiri”).7
During the Quarter, Equinaire proceeded to issue a series of notices to MHL relating to claimed
Events of Default, Foreclosure Proceedings and Disposition.8
Celsius refutes the occurrence and continuance of an Event of Default under the OLSA and the
capacity of Equinaire to initiate a foreclosure process and sell its interest in MMCI. It believes
that the claimed Events of Default should be referred to arbitration in accordance with the
dispute resolution clauses within the OLSA.
Notwithstanding Celsius’ objections, on 8 September 2026, Equinaire proceeded to conduct the
public auction for the foreclosure of MHL’s shares in MMCI, which were pledged as collateral
under the OLSA.
Representatives from MHL were in attendance to put on record that any results of the foreclosure
sale remain subject to the final determination of the pending arbitration between MHL and
Equinaire.
Equinaire submitted a credit bid of US$5,010,000. As there were no other registered bidders in
attendance and no other bids received, Equinaire was declared the winning bidder.9
Tax clearance
On 28 October 2026, Kiri announced that the Philippine Bureau of Internal Revenue (“BIR”)
had issued an Electronic Certificate Authorizing Registration (“eCAR”) in relation to the
transfer of 40% of MMCI shares held by MHL to Equinaire and that the transfer of shares had
been recorded in the Stock and Transfer Book of MMCI.10
Celsius had previously notified the BIR in writing regarding the pending dispute between
MHL and Kiri and highlighted the uncertainty surrounding the validity of the foreclosure sale.
In response to the written notice from Celsius, the BIR while noting that it is not making any
binding determination on the ultimate validity of the foreclosure sale or adjudicating the
parties' respective civil rights, it emphasised that the pending dispute does not, by itself,
preclude the processing of the eCAR, and as a result, issued the contested eCAR with
manifest haste in a manner exceeding its standard processing times.
7
See 9 June 2026 ASX / AIM Announcement – Assignment of MIC OLSA to Kiri.
8
See 2 September 2026 ASX / AIM Announcement – Corporate update; 27 August 2026 ASX / AIM Announcement –
Corporate update; 12 August 2026 ASX/AIM Announcement – Further MMCI OLSA Update; and 20 July 2026
ASX/AIM Announcement – MMCI OLSA Update.
9
See 9 September 2026 ASX / AIM Announcement – Corporate update.
10
See 30 October 2026 ASX / AIM Announcement – Corporate update.
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
5
Petition for Interim Measures of Protection
A Petition for Interim Measures of Protection (“Petition”) was previously filed with a Philippine
Court, seeking to injunct any foreclosure of the OLSA or disposition of Celsius’ interest in MMCI
until the conclusion of arbitration between the parties.
The Court denied the Petition, finding that "irreparable injury” had not been sufficiently
established and determining that any potential loss arising from the foreclosure could be
addressed through remedies available in arbitration.
However, the Court expressly stated that the denial of the Petition is not a determination that an
Event of Default occurred or that Equinaire was entitled to foreclose. The Court likewise
recognised that these issues remain disputed and should be addressed via arbitration. The
Court further emphasised that the arbitral tribunal has authority to determine the validity of any
foreclosure and, where appropriate, grant interim relief.
A Motion for Reconsideration was filed by MHL, but was denied by the Court.
Given the expediency of the eCAR issuance, and the subsequent recording of the share transfer
in MMCI’s Stock and Transfer Book, there is no longer any merit elevating the matter to the Court
of Appeals.
Instead, Celsius is planning to file another Application for Interim Measures of Protection as part
of the arbitral proceedings with Sodor, which would seek to injunct MMCI from proceeding with
any material transactions or contracts (including an offtake agreement, materially amending
the company’s articles or by-laws, or selling any material MMCI assets). It also intends to file a
new petition for an interim measure of protection with the court against Equinaire in the form of
attachment or receivership, which would prevent Equinaire from selling the disputed shares in
MMCI to a third-party.
Criminal case against Attorney Sarmiento
Background
Attorney Sarmiento is a former Executive Chair of Celsius and has been acting as an adviser to
Kiri, Sodor and PMR and their key principals in relation to MMCI and the MCB Copper-Gold
Project.
His numerous roles, relationships and dealings with parties associated with MMCI include:
• Former Executive Chair of Celsius (he retired at the Annual General Meeting on 26 November
2025)11
;
• Representative of MHL (a wholly owned subsidiary of Celsius) on the MMCI Board (he
resigned on 20 April 2026);
• Sodor’s appointee on the MMCI Board (he was re-appointed on 20 April 2026);
• Chair and President Director of MMCI;
• An executive consultant to MMCI (appointed for a period of 5 years in May 2025 with a
monthly fee of US$25,000);
11
See 13 October 2025 ASX/AIM Announcement – Executive Chairman to retire from the Board at 2025 AGM.
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
6
• Founding Partner and Co-Managing Partner of Sarmiento Loriega Law (“SL Law”), noting that
o His co-partner at SL Law, Mr Recolito “Ricky” Cantre, was a Celsius appointee on the MMCI
Board (he resigned on 20 April 2026);
o SL Law previously acted as MMCI’s principal Philippine legal adviser under the direction
and supervision of Attorney Sarmiento;
o SL Law led the drafting and negotiation of the legal agreements entered into with Sodor
and PMR that are now subject to arbitration;
o SL Law led the drafting and negotiation on the MMCI OLSA with MIC, which was signed by
Attorney Sarmiento on behalf of MMCI, which has been recently assigned to Kiri;
o Kiri and companies associated with Sodor, PMR and their principals are established
clients of SL Law; and
• Following the reconstitution of the MMCI Board, three employees from SL law were appointed
to the MMCI management team. In addition, five representatives from SL Law were also
granted access to information, supervision rights and responsibilities in relation to the
operation of MMCI.
At the time of Attorney Sarmiento’s retirement from the Celsius Board, there was a dispute with
respect to a 3% finder’s fee that SL Law had claimed in relation to the MIC OLSA. Concerns had
been raised by the Celsius and MMCI Boards in relation to potential related party considerations,
whether there had been adequate disclosure of the arrangement to the Celsius Board ahead of
approaching MIC and whether Attorney Sarmiento engaged with MIC in his capacity as the
Executive Chair of Celsius and President Director of MMCI or as the Founding partner of SL Law.
Attorney Sarmiento’s remuneration from Celsius and MMCI for Financial Years 2023/24 and
2024/25 was A$520,608 (US$371,193) and A$513,498 (US$366,124), respectively.12
Since Attorney Sarmiento was reappointed to the MMCI Board as Sodor’s nominee and re-
appointed as President and Chair of MMCI, a series of actions have been undertaken, which have
prejudiced the Company’s interests. Celsius alleges that these include:
• Breaches of MMCI’s By-Laws and the Revised Corporation Code (“RCC”) with respect to
irregularities in the calling of an MMCI Stockholders Meeting;
• Unlawfully removing Celsius’ MMCI board representation (which requires the approval of
two-thirds of outstanding capital under the RCC);
• Unlawfully removing corporate records from MMCI principal office and relocating those
records to the office of SL Law; and
• Unlawfully restricting Celsius’ access to MMCI’s corporate records; and
• Preventing Celsius from voting at a MMCI Stockholder’s Meeting that was called to
consider the approval of an increase in the authorised capital stock of MMCI.
Celsius has concerns around the conduct of both Attorney Sarmiento and SL Law including
with respect to potential contraventions of law, the management of conflicts (including the
12
References to US$ equivalents are based on A$/US$ exchange rate of 0.713.
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
7
disputed “finder’s fee” outlined above), breaches of confidentiality and fiduciary duties as well
as potential violations of professional responsibility and accountability rules.
Anti Dummy Law case against Attorney Sarmiento
During the Quarter, Celsius commenced criminal proceedings against Attorney Sarmiento via
the lodgement of a complaint-affidavit with the Philippines Department of Justice, which alleges
a contravention under Section 2-A of the Anti-Dummy Law. This covers contraventions of a
requirement under either the Philippine Constitution or Philippine laws for 60% ownership by
Philippine nationals and entities. This law extends to aiding, assisting or abetting in the
“planning, consummation or perpetration” of a breach.
The alleged contravention relates to an email sent by Attorney Sarmiento (in his capacity as
Founding Partner and Co-Managing Partner of SL Law) to Mr Manish Kiri, the Chairman and
Managing Director of Kiri, his colleague Mr Hemil Kiri, and also to Ms Carisa Sari, a Sodor-
nominated member of MMCI’s Board of Directors. Mr Suresh Gondalia, Kiri’s Company Secretary,
also appeared in the email exchanges. In the context of SL Law providing Kiri with advice on the
establishment of Philippine subsidiaries, Attorney Sarmiento communicated the following:
“As I explained in our update meeting yesterday, Carabao Corporation as the holding company,
will in turn be creating special project vehicles (SPVs), as and when, you enter and make actual
investments in any industry, such as, but not limited to,
1. mining (i..e, Carabao Mining Corporation);
2. Waste technology (i..e, Carabao Waste Technology Corporation);
3. Agriculture (i.e., Carabao Agri-Business Corporation); and
4. Renewable Energy (Carabao Energy Corporation).
And so on and so forth. If the SPV is required to be a Filipino company with 60% Filipino and 40%
foreign, then the SPV will be structured in such a manner that the 60% will be held by trusted
Filipinos (e.g., our SL Law Partners) who will need to sign Deeds of Trust and undated Deeds of
Assignment to ensure you retain full control of the SPV, while the 40% will be held by your
holding company, Carabao Corporation.”
Celsius contends that this is a clear and deliberate attempt to breach the provisions of Section
2-A of the Anti-Dummy Law. It also raises important questions around the bona fides of both SL
Law and Kiri in relation to ongoing arbitration cases.13
Disbarment case against Attorney Sarmiento
Following the filing of the criminal complaint outlined above, Celsius and other complainants
filed a verified disciplinary complaint seeking the disbarment of Attorney Julito “Sarge” R.
Sarmiento (“Attorney Sarmiento”) and other respondent lawyers from SL Law for alleged
violations of the Code of Professional Responsibility and Accountability.14
The other senior respondents from SL Law include:
• Attorney Maria Elizabeth “Beth” E. Peralta-Loriega (Founding Partner and the Co-Managing
Partner);
13
See 20 July 2026 ASX/AIM Announcement – MMCI OLSA update
14
See 24 August 2026 ASX / AIM Announcement – Disbarment application filed against Attorney Sarmiento.
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
8
• Attorney Recolito Ferdinand “Ricky” N. Cantre, Jr. (Senior Partner);
• Attorney Jose A. Linsangan (Senior Partner);
• Attorney Bryan A. San Juan (Senior Partner); and
• Attorney Christine C. Clemente (Partner).
In addition, several junior lawyers were also named in the disciplinary disbarment complaint.
Estafa case against Erika Chalmers
In October 2026, Celsius and its wholly owned subsidiary, Makilala Holding Limited ("MHL"), filed
a criminal complaint against Ms. Erika I. Chalmers, the President of Sodor, in the Office of the City
Prosecutor of Pasig City, under the Department of Justice of the Philippines (“DOJ”).15
The primary criminal complaint is for Estafa, which is defined and penalised under Article
315(2)(a) of the Revised Penal Code of the Philippines (“RPC”). Under Philippine law, Estafa (also
referred to as swindling) occurs when a person defrauds another person through deceit or by
abusing their trust, resulting in financial damage or prejudice.
The secondary or alternative criminal complaint is for Other Deceits, which is defined and
penalised under Article 318 of the RPC. Under Philippine law, Other Deceits is a broad "catch-all"
offense covering fraudulent acts that cause financial damage or prejudice but do not meet the
strict, specific technical requirements of Estafa.
Both complaints relate to issues associated with Sodor’s acquisition of shares in MMCI on
account from MHL.
Subsequent to the filing of the criminal complaint, Celsius understands that the City Prosecutor
of Pasig City conducted a preliminary investigation on 22 October and 29 October 2026.
SEC complaint
During the Quarter, Celsius filed a complaint with the Philippine Securities and Exchange
Commission (“SEC”) with respect to being unlawfully restricted from accessing MMCI’s
corporate records.16
Celsius and MMCI subsequently filed their respective position papers and are awaiting a
decision by the SEC.
General Meeting
Celsius held a General Meeting of shareholders on 9 September 2026.
Key outcomes included:
• New constitution: A special resolution was passed to adopt a new constitution compliant
with the Corporations Act 2001, updating provisions around share capital, restricted
securities, and electronic transfers;
• Share consolidation: The proposed cancellation of the share consolidation was approved;
and
15
See 8 October 2026 ASX / AIM Announcement – Filing of Criminal Complaint for Estafa Against Erika Chalmers.
16
See 3 August 2026 ASX / AIM Announcement – Filing of Criminal Complaint Against Attorney Sarmiento.
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
9
• Securities: Shareholders approved the issue of director performance rights and
consideration shares to Managing Director, Bardin Davis, and various placement and broker
options.
Continued momentum across key MCB Project workstreams
During the Quarter, key MCB Project activities included the following:
• Project development activities – continued coordination with the Municipality of Pasil with
respect to a construction permit and the Memorandum of Agreement, receipt of an EPC
proposal, preparations for a tender process for an internal access road, and road access
planning with the Provincial Government;
• Environmental management – propagation of 89,906 seedlings, continued environmental
monitoring and rehabilitation, and co-ordinated the collection of a material amount of
waste during World Cleanup Day;
• Health and safety - recorded 21,470 safe man-hours (1,034,875 cumulative hours), with zero
recorded accidents or work-related illnesses since 2021, and completed safety inspections,
toolbox meetings, and an earthquake drill; and
• Social Development - completed the Ma-alinao Level III Potable Water System, initiated
repairs to the Tuwer Suspension Footbridge, and continued education, medical assistance,
and community engagement activities.
Sagay Copper-Gold Project, Philippines
Key activities undertaken during the Quarter at the Sagay Copper-Gold Project included:
• Ongoing co-ordination with government agencies, consultants, and other stakeholders in
support of outstanding regulatory deliverables;
• Continued advancement of the environmental permitting process, regulatory compliance,
and tenement-related requirements;
• Acceptance of the Environmental Impact Statement by the Environmental Management
Bureau Central Office and completion of the First Environmental Impact Assessment Review
Committee Meeting; and
• Finalisation of a Mineral Land Survey in support of the pending Declaration of Mining Project
Feasibility (“DMPF”).
Botilao Copper-Gold Prospect, Philippines
No major field activities were undertaken during the Quarter, other than ongoing stakeholder
engagement.
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
10
Cash position
At the end of the quarter, the Company held approximately A$ 5.36 million in cash reserves.
ASX additional information
The Company provides the following information pursuant to ASX Listing Rule requirements:
• ASX Listing Rule 5.3.1:
Approximately A$169,000 was spent on exploration expenditure during the quarter, primarily
relating to the development of the MCB and Sagay Projects.
• ASX Listing Rule 5.3.2:
Nil was spent on mine production and development activities during the quarter.
• ASX Listing Rule 5.3.5:
The payments to related parties disclosed at section 6.1 of the Appendix 5B relate to director
fees and consultancy services during the period.
Tenement Table: ASX Listing Rule 5.3.3 - mining tenement interests held at the end of the
quarter and their location
Permit
name
Permit
number
Registered
holder /
applicant
Permit
status
Permit
expiry
Interest /
contractual
right
Namibia
Opuwo EL 4346
Gecko Cobalt
Holdings
Awaiting
issuance of
tenement permit
TBA1
95%
Philippines
Maalinao-
Caigutan-
Biyog
MPSA-356-
2024-CAR
Makilala Mining
Company Inc.
Granted 13/03/2049 40%
Botilao
EP-011-
2023-CAR
Makilala Mining
Company Inc.
Granted 27/01/2028 40%
Panaon
EXPA-
000127-VIII
PDEP, Inc.
Complying with
further
requirements
TBA 100%
Sagay
EP-000003-
VI
Tambuli Mining
Company Inc.
Granted
Automatic
extension
until the
approval of
the
DMPF/MPSA
100%
Note: 1. The Exclusive Prospecting Licence for the Opuwo Project was subsequently extended to 8 October
2028.
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
11
Key information on the mining tenements:
• Beneficial percentage interests held in farm-in or farm-out agreements at the end of the
Quarter: not applicable; and
• Beneficial percentage interests in farm-in or farm-out agreements acquired or disposed of
during the Quarter: nil.
This announcement has been authorised by the Board of Directors of Celsius Resources Limited.
The information contained within this announcement is deemed by the Company to constitute
inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 as it
forms part of UK Domestic Law by virtue of the European Union (Withdrawal) Act 2018.
For further information contact:
Celsius Resources Limited
Bardin Davis - Managing Director E: info@celsiusresources.com.au
W: www.celsiusresources.com
Media – Purple Communications Pty Ltd
Andrew Edge M: +61 410 276 744
E: aedge@purple.au
Zeus
Nominated Adviser -
James Joyce/James Bavister
Broking - Harry Ansell
P: +44 (0) 20 3 829 5000
Zeus Capital Limited (“Zeus”) is the Company’s Nominated Adviser and is authorised and regulated by the
FCA. Zeus’s responsibilities as the Company’s Nominated Adviser, including a responsibility to advise and
guide the Company on its responsibilities under the AIM Rules for Companies and AIM Rules for Nominated
Advisers, are owed solely to the London Stock Exchange. Zeus is not acting for and will not be responsible
to any persons for providing protections afforded to customers of Zeus nor for advising them in relation
to the proposed arrangements described in this announcement or any matter referred to in it.
ASX RELEASE | QUARTERLY REPORT | 30 September 2026
12
Compliance statements
For the information in this announcement that relates to exploration results that have been previously
released to ASX, the Company confirms that it is not aware of any new information or data that materially
affects the information included in the original ASX announcement and that all material assumptions and
technical parameters continue to apply.
The Company confirms that it is not aware of any new information or data that materially affects the
Mineral Resource Estimate for the MCB17
Project, the Sagay18
Project or the Opuwo19
Project. The Company
also confirms that all material assumptions and parameters underpinning the Mineral Resource Estimate
continue to apply and have not materially changed. The form and context in which the relevant Competent
Person’s findings are presented have not been materially modified from the original document.
The Company confirms that it is not aware of any new information or data that materially affects the Ore
Reserve Estimate for the MCB Project20
. The Company also confirms that all material assumptions and
parameters underpinning the Ore Reserve Estimate continue to apply and have not materially changed.
The form and context in which the relevant Competent Person’s findings are presented have not been
materially modified from the original document.
Forward looking statements
Some of the statements appearing in this announcement may be in the nature of forward-looking
statements. You should be aware that such statements are only predictions and are subject to inherent
risks and uncertainties. Those risks and uncertainties include factors and risks specific to the industries in
which the Company operates and proposes to operate as well as general economic conditions, prevailing
exchange rates and interest rates and conditions in the financial markets, among other things. Actual
events or results may differ materially from the events or results expressed or implied in any forward-
looking statement.
No forward-looking statement is a guarantee or representation as to future performance or any other
Share your feedback
Discover