Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
Quarterly Activities Report
For the quarter ended 30 June 2026
1
Celsius Resources Limited (“Celsius” or the “Company”) (ASX, AIM: CLA) continued its focus on
the Maalinao-Caigutan-Biyog Copper-Gold Project (“MCB Project”) during the June 2026
Quarter (“Quarter”) with the following recent milestones and events occurring:
George Bujtor appointed as Chair
The appointment of George Bujtor as Non-Executive Chair of Celsius was announced on 14 July
2026.1
George is a highly distinguished mining executive with over 50 years of technical, commercial
and leadership experience across the global resources sector. His appointment brings strong
technical expertise, senior leadership and governance experience and a proven track-record in
successfully funding, developing and operating Philippine mining projects.
He spent over 25 years with Rio Tinto, holding senior technical, development, and commercial
roles in Australia. George has been predominantly based in the Philippines since 2005, and has
held a series of senior roles within the Philippine mining sector, including as Managing Director
of both Toledo Mining Corporation plc (“Toledo Mining”) and Carmen Copper Corporation
(“Carmen Copper”).
During his time with Toledo Mining, Mr Bujtor oversaw the successful funding and development
of the Berong Nickel Laterite Project. As Managing Director of Carmen Copper, he led the ramp-
up to full production of the rehabilitated Carmen Copper Project, the optimisation of by-product
production and a US$300 million financing.
1
See 14 July 2026 ASX / AIM Announcement – Experienced Mining Executive George Bujtor Appointed Chair.
• Experienced mining executive, George Bujtor, appointed as Chair
• Opuwo Project to be sold to Chinalco for US$15 million
• Renewed attention on the Sagay Copper Project
• New Company Secretary and CFO appointed
• Proposed cancellation of share consolidation
• Transfer of MMCI loan from MIC to Kiri
• Arbitration initiated to protect Celsius’ interests in the MCB Project
• Continued momentum across MCB Project workstreams
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
2
Non-Executive Chair,
George Bujtor
“I have long recognised the high quality of Celsius’ MCB
Project and its wider portfolio in the Philippines. This is a
pivotal time for the Company, and I look forward to
working closely with the Board and management to
resolve the current MMCI arbitration and rapidly advance
the MCB Project toward development."
Peter Hume has stepped down as Interim Non-Executive Chair and remains on the Celsius Board.
Opuwo Project to be sold to Chinalco for US$15 million
During the Quarter, Celsius executed a binding Share Sale Agreement (“SSA”) with Chinalco
(Xiong’an) Mining Corporation Limited (“Chinalco (Xiong’an) Mining”), a subsidiary of Aluminum
Corporation of China (“Chinalco”), in relation to a sale of its 95% interest in the Opuwo Cobalt-
Copper Project (“Opuwo Project”) in Namibia.
The Opuwo Project is a large-scale, advanced cobalt-copper exploration and development
Project located in the Kunene Region of North-Western Namibia.
The divestment will enable Celsius to increase its focus on its Philippine portfolio of copper-gold
projects and provide a material source of near-term funding. Subject to resolving the current
arbitration dispute with respect to Makilala Mining Company, Inc (“MMCI”), Celsius intends to
utilise the net proceeds from the proposed sale to progress the development of the MCB
Copper-Gold Project.
The transaction entails the sale of an intercompany loan and Celsius’ 95% interest in Opuwo
Cobalt Holdings (Proprietary) Limited (“Opuwo Cobalt Holdings”) for total consideration of US$15
million (~A$21.7 million).2
Chinalco (Xiong'an) Mining is a specialised non-ferrous subsidiary of Chinalco that is focused
on the development of large-scale international base metals projects.
A condition precedent relating to a waiver of pre-emptive rights held by the 5% minority
shareholder of Opuwo Cobalt Holdings has been satisfied.
Remaining transaction conditions precedent include:
• Celsius shareholder approval (required under Rule 15 of the AIM Rules for Companies);
• Renewal of the Exclusive Prospecting Licence (“EPL”) and Environmental Clearance
Certificate (“ECC”);3
• Approval by the Namibian Competition Commission and Bank of Namibia (in relation to
exchange controls);
2
Based on A$/US$ exchange rate of 0.69.
3
Applications for a renewal of the EPL and ECC have been made with the relevant Namibian authorities.
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
3
• Clearance by the Chinese National Development and Reform Commission (“NDRC”), Ministry
of Commerce (“MOFCOM”) and Bureau of Foreign Exchange Administration (“SAFE”);
• Warranties remaining true and correct; and
• No material adverse effect.
As a demonstration of its commitment to the transaction and the Opuwo Project and in support
of EPL and ECC renewal applications, Chinalco (Xiong’an) Mining has agreed to provide a non-
refundable exploration commitment of a minimum of US$750,000 on exploration and
US$250,000 on metallurgical test work while conditions precedents are being satisfied (with the
results to be provided to Celsius and to support the EPL renewal).
Renewed attention on the Sagay Copper Project
During the Quarter, Celsius announced that its wholly owned subsidiary, Tambuli Mining
Company, Inc. (“Tambuli”):
• Appointed Attilenore “Nene” Manero – as Interim Chair and President; and
• Intends to appoint Peter Hume – as Technical Advisor upon finalisation of applicable
regulatory and administrative requirements.4
Tambuli is focused on progressing the Sagay Copper Project, which is located in the north-
eastern part of Negros Island, within the Province of Negros Occidental, Philippines.
These appointments follow the recent termination of Nene Manero as Chief Sustainability
Director of MMCI and Peter Hume as Technical Director of MMCI by Mr Julito “Sarge” Sarmiento
in his capacity as President Director of MMCI.5
They will enable Celsius to retain critical in-country expertise and experience, and support the
longer-term strategy of progressing the development of the Sagay Copper Project.
4
See 9 June 2026 ASX / AIM Announcement – Tambuli Mining Appointments.
5
See 25 May 2026 ASX / AIM Announcement – Corporate Update.
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
4
Sagay Project location and snapshot
• Tenement area ~1,780 hectares
• Main deposit - large-scale deep copper-
gold porphyry
• Secondary deposit - shallow supergene
deposit west of the main porphyry, which
would be the first target to be developed
• Exploration - commenced in 2008
• Completed drilling - 47 drill holes and
28,252m completed between 2012 to 20236
• Mineral Resource Estimate - 312Mt @ 0.39%
copper and 0.11g/t gold (~1.2Mt of contained
copper and ~1Moz of contained gold)7
Potential development approach
The Sagay Project is intended to be developed in two phases.
Phase 1 - initial development of the shallow supergene copper deposit.
A Mining Project Feasibility Study was submitted to the Philippine Mines and Geosciences Bureau
(“MGB”) on 20 December 2023, which entailed:
• Medium-scale surface mining operation (mine footprint limited to ~20 hectares);
• Processing of ore through gravity separation (avoiding the need for chemical reagents
and flotation agents);
• Dry-stacking of tailings to eliminate the need for a tailings dam; and
• Production of a highly marketable copper concentrate with have no material deleterious
elements.
Phase 2 - potential future development of the large-scale deep copper-gold porphyry.
Subject to the support of the local community and further technical studies, Celsius intends to
assess the longer-term potential for developing the large-scale copper porphyry project
comprising of:
• An underground block cave mining operation; and
• Processing of ore and the production of a copper-gold concentrate via a standard
milling and flotation operation.
6
See 6 February 2024 ASX / AIM Announcement – Mineral Resources update for Sagay Mining Project.
7
Reflects the combined Measured, Indicated and Inferred Mineral Resource (see announcement above).
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
5
Status
A Declaration of Mining Project Feasibility (“DMPF”) application has been submitted with the
Philippine Mines and Geosciences Bureau (“MGB”) and an updated Environmental Impact
Assessment (“EIA”) has been submitted to the Department of Environment and Natural
Resources (“DENR”).
Next steps include:
• Undertaking a Technical Review Committee evaluation meeting and subsequent public
hearing as part of the Philippine EIA Process;
• Grant of an Environmental Compliance Certificate ("ECC") following the satisfactory
completion of the Philippine EIA Process;
• Approval of the Declaration of Mining Project Feasibility ("DMPF"), including the review and
endorsement of the project's technical, environmental, social and financial readiness by the
relevant government authorities; and
• Completion of the remaining statutory requirements and permitting processes associated
with the grant of either a Mineral Production Sharing Agreement ("MPSA") or a Financial or
Technical Assistance Agreement ("FTAA").
New Company Secretary and CFO
During the Quarter, Ian Hobson was appointed as Celsius’ Company Secretary and Chief
Financial Officer.
Company Secretary
and CFO, Ian Hobson
Ian Hobson is a Chartered Accountant and Chartered
Company Secretary with 40 years’ experience in the
profession. Ian was a director at PricewaterhouseCoopers for
many years with experience working in Australia, UK and
Canada. Ian now provides company secretary services and
undertakes corporate, management and accounting
positions with a number of listed public companies.
MMCI loan update
During the Quarter, the Philippine sovereign wealth fund, Maharlika Investment Corporation
(“MIC”) completed the assignment of its rights, title, and interests under the Omnibus Loan and
Security Agreement (“OLSA”) with Makilala Mining Company Inc. (“MMCI”) to Equinaire Holdings
Limited (“Equinaire”), a wholly-owned subsidiary of Kiri Industries Limited (“Kiri”) of India.8
Kiri provided the following rationale for acquiring the OLSA:
8
See 9 June 2026 ASX / AIM Announcement – Assignment of OLSA to Kiri, 25 May 2026 ASX / AIM Announcement –
Corporate Update, 30 April 2026 - ASX / AIM Announcement – Update on potential assignment of MIC OLSA, and 27
April 2026 ASX / AIM Announcement – Potential assignment of MIC OLSA.
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
6
“The acquisition of the loan represents a precursor transaction that is expected to enable the
Group to benefit from an off-take arrangements, ensuring preferential supply of copper
ore/concentrate from Makilala Mining Company, Inc. for its upcoming copper facility being
developed by Indo Asia Copper Limited.”9
Further to the acquisition and assignment of the OLSA, Equinaire issued the following notices on
Friday 17 July 2026:
• Notice of Event of Default – which claims that the Notice of Relinquishment issued to Sodor,
Inc. (“Sodor”) constituted an Event of Default under the OLSA;
• Notice of Commencement of Foreclosure Proceedings – which on the basis of Equinaire’s
claimed Event of Default, is seeking to initiate a foreclosure process and the enforcement of
security with respect to Celsius’ 40% interest in MMCI; and
• Notice of Disposition – which is seeking to initiate a public auction for Celsius’ 40% interest in
MMCI.
Celsius refutes the occurrence of an Event of Default and the capacity of Equinaire to initiate a
foreclosure process and sell its interest in MMCI. It intends to protect its interests to the fullest
extent of the law.
Proposed cancellation of the share consolidation
At a General Meeting on 30 April 2026 shareholders approved the consolidation of the
Company's issued capital on a 20-for-1 basis.
The Company subsequently announced that following recent developments and shareholder
feedback, the Board no longer believes that it is currently in the best interests of shareholders to
proceed with the consolidation.10
In that regard, the Board intends to seek shareholder approval
at an upcoming general meeting (anticipated to be held in early September 2026) to formally
rescind the approval obtained by shareholders at the General Meeting for the Consolidation
(“Revocation Resolution”).
If the Revocation Resolution is passed, the Consolidation will not proceed and there will be no
change to the Company's capital structure.
If the Revocation Resolution is not passed, the Consolidation will continue to proceed in
accordance with a revised timetable.
Dispute in relation to the ownership of the MCB Project
Previously contemplated transaction
The following ownership arrangements for the MCB Project were agreed via binding deeds and
agreements on 17 March 2023:
9
See 30 April 2026 ASX / AIM Announcement – Update on potential assignment of MIC OLSA.
10
See 26 June 2026 ASX / AIM Announcement – Securities Consolidation Update.
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
7
• Sodor was to acquire a 60% legal ownership in MMCI for consideration of PHP 300 million
(~US$5 million);
• PMR, an affiliate of Sodor, was to subscribe for shares in PDEP Inc. (“PDEP”), the intended
mineral processing company for the MCB Project, for an amount of ~US$38 million
(comprising of ~US$43 million less the PHP 300 million subscription in MMCI by Sodor); and
• These arrangements were to be relinquished, if Sodor and PMR had not provided the required
payment within two years, unless shortened or extended by mutual agreement.11
The MCB Project was to be owned and operated via the following two entities:
• MMCI - which would hold the MPSA and develop and operate the mine; and
• PDEP - which would own, develop and operate the processing plant and other ancillary
equipment and assets, and would not be subject to foreign ownership restrictions.
Upon completion of the payment of the ~US$43 million, Sodor and PMR were to hold a combined
30% share in the economics of the MCB Project with Celsius retaining a 70% share of economics.
Further to the execution of agreements with Sodor and PMR, the expiry date for the payment of
~US$43 million was extended to 16 February 202612
.
Following the expiry of this deadline, Celsius provided written notice to Sodor that the MMCI
shares must be relinquished in accordance with the agreement.
Notwithstanding the expiry of the payment deadline (and the provision of the notice to Sodor
outlined above), Sodor subsequently (being ~30 days following expiring deadline) attempted to
pay the outstanding amount of PHP 300 million (~US$5 million) and a notice was received from
PMR stating that it had sufficient funding to complete its subscription of shares in PDEP.
Socialej
Ahead of this expiry date, Celsius considered a range of alternate transaction structures and
potential replacements for Sodor.
One of the candidates that was initially considered as a replacement for Sodor was Socialej Inc.
(“Socialej”), a Philippine incorporated entity, in which Celsius’ Interim Non-Executive Chair, Mr
Peter Hume and former Celsius Non-Executive Director, Ms Attilenore “Nene” Manero held equity
interests.13
The board of directors of both Celsius and Socialej declined to progress a potential transaction
due to governance and related party concerns.
11
Full details of the agreements and the intended interests of each party’s interests in MMCI and PDEP are set out in
the 20 March 2023 ASX / AIM Announcement – CLA enters Binding Deed with local companies for MCB Project.
12
See 27 June 2025 ASX / AIM Announcement – FEED and Feasibility Update commence at MCB Project site.
13
These interests were disclosed to the Celsius Board.
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
8
Notwithstanding these decisions and without any approval or authority from either entity, Mr Neil
Grimes, issued Sodor on 16 February 2026 with a notice of relinquishment, that included directing
Sodor to transfer its shares in MMCI to Socialej.14
Mr Neil Grimes’ executive consulting agreement was terminated by the Board on 3 May 202615
with immediate effect and he agreed to tender his resignation as a Director of Celsius on 11 May
202616
.
Celsius is not seeking to transfer Sodor’s shares in MMCI to Socialej and subject to the outcome
of the arbitration process, it intends to transfer the shares to a suitably qualified independent
Philippine party.
Arbitration
Further to Celsius rejection of Sodor’s attempted payment, Sodor and PMR initiated an
emergency arbitration process and sought an interim order to prevent the sale or transfer of
MMCI shares to another party.
On 21 April 2026, the initial conflict resolution process was concluded in Celsius’ favour with the
interim orders sought by Sodor and PMR being denied.
To further protect its interests, Celsius initiated an emergency alternative conflict resolution
process and applied for the following interim orders:
• Prevention of Sodor from exercising any rights as a shareholder or as a director of MMCI;
• Maintenance of the status quo until the determination of a broader conflict resolution
process; and
• In the event of Sodor requisitioning a shareholders meeting, Sodor and any of its nominees
being restricted from implementing any actions or resolutions passed until the
determination of a broader conflict resolution process has been completed.
Notwithstanding Celsius’ emergency application to preserve the status quo until the finalisation
of the broader arbitration process, and in advance of its completion, the following actions were
subsequently undertaken:
• Mr Sarmiento resigned his position as a representative of Makaila Holding Limited (“MHL”), a
100% owned subsidiary of Celsius, to the MMCI Board as well his position as Chair and
President of MMCI on 20 April 2026; and
• Sodor requisitioned a MMCI stockholder’s meeting, which was held on 20 April 2026, during
which a series of resolutions were passed including:
o all five board seats being declared vacant;
14
The Celsius Board approved the issuance of a notice of relinquishment, but not the transfer of shares to Socialej.
15
See 4 May 2026 ASX/AIM Announcement – Update on alternative conflict process.
16
See 11 May 2026 ASX/AIM Announcement – Resignation of Non-Executive Director.
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
9
o Sodor appointing three representatives to the MMCI Board, including Mr Sarmiento, who
was also re-appointed as Chair and President;
o the preventative suspension of key MMCI employees; and
o appointment of a new company secretary and several executive officers.
On 5 May 2026, the interim orders sought by Celsius were denied. The basis for the decision was
that the status quo, being that Sodor continues to hold its 60% interest in MMCI, should prevail
until the broader arbitration process has concluded.
At a subsequent stockholders meeting convened by Sodor, Sodor proceeded to appoint a
further two nominees to the MMCI Board.
Celsus contends that there were breaches of MMCI’s By-Laws and the Revised Corporation Code
of the Philippines (“RCC”) with respect to the calling of both stockholders’ meetings and in the
removal of Celsius’ MMCI board representation (which requires the approval of 2/3 of
outstanding capital).
Both Celsius as well as Sodor and PMR have initiated broader arbitration proceedings.
Celsius is seeking to enforce the relinquishment of the Sodor and PMR arrangements, which
would enable it to progress the transfer of Sodor’s shares in MMCI to a new qualified independent
Philippine partner.
Sodor and PMR are seeking a range of orders that include the following:
• Recognition of Sodor's legal ownership of 60% of MMCI;
• Invalidation of the notice of relinquishment issued to Sodor by MHL;
• PMR’s obligation to subscribe for shares in PDEP is not enforceable and demandable in the
absence of:
o A signed Memorandum of Agreement (reflecting the terms of the Term Sheet executed
between the parties in December 2022);17
o A finalised Subscription Agreement;
o Mutually agreed schedule governing tranche payments;
o Sufficiency of authorised capital stock of PDEP; and
• PMR’s subscription price of ~US$38 million to be held by MMCI and used exclusively for the
development of the MCB Project.
17
For further details see 20 March 2023 ASX / AIM Announcement – CLA enters Binding Deed with local companies
for MCB Project.
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
10
Continued momentum across key MCB Project workstreams
During the Quarter, MCB Project activities focused on advancing project readiness through mine
plan refinement, contractor engagement, infrastructure planning, power supply connection
evaluation, and permitting workstreams.
Underground mine development
Technical assessments were undertaken to identify and evaluate potential modifications to the
mine development strategy. Various mine sequencing, underground access, and development
alternatives were reviewed to determine opportunities for earlier access to higher-grade
mineralised areas, with the objective of enhancing project economics, optimising cash flow
generation, and improving overall project value.
Process Plant including civil works
Prospective mining contractors were approached around future mine process plant
construction development and operational support. A Civil, Structural, Mechanical, Piping,
Electrical, and Instrumentation (“CSMP&EI”) scope was issued to contractors who had submitted
expressions of interest. Engagement centred on clarifying technical requirements, addressing
queries, and refining the proposed scope of work.
Main Access Road
A survey of the proposed alignment of the road between from Balatoc to the vicinity of Mt.
Sapukoy has been completed. The preliminary engineering is targeted to be completed next
quarter.
Power supply and infrastructure
Discussions were held with power companies to explore potential power supply solutions and
identify the most viable pathway for meeting the project’s future energy requirements.
Discussions focused on infrastructure considerations and possible implementation strategies to
ensure an efficient and sustainable power solution for future operations.
Site Investigations and Water Resource Assessment
Site investigation activities focused on groundwater monitoring and hydrological assessments.
Groundwater levels were routinely measured and analysed to evaluate groundwater pressure
trends, seasonal fluctuations, and subsurface hydraulic responses.
To support operational water requirements and ongoing water balance assessments, additional
investigations were undertaken to identify and evaluate potential long-term water sources.
Ongoing commitment to the MCB Project community and local stakeholders
Key initiatives under the Social Development and Management Program were implemented,
using funding from the MMCI OLSA, in support of the project’s commitments to its host
communities and in advancing sustainable and inclusive development.
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
11
Community-based skills training
The Technical Education and Skills Development Authority (“TESDA”) assessment for the second
batch of Masonry NC II Training Program was successfully conducted, supporting 22 graduates,
composed of 16 males and 6 females. The assessment served as the final validation of the
participants' competencies and practical skills acquired throughout the training program.
Through this process, the graduates earned industry-recognized National Competency
Certifications, significantly enhancing their employability and capacity to contribute to local
workforce development.
Since the implementation of MMCI’s skills development initiatives in 2025, a cumulative total of
118 TESDA National Competency Certifications has been awarded to qualified participants from
the Balatoc community, achieving an outstanding 100% assessment passing rate. This reflects
both the effectiveness of the training programs and MMCI’s continued commitment to building
a skilled, competitive, and empowered local workforce.
Educational assistance and scholarship program
Educational assistance for the 2nd Semester of School Year 2025–2026 was successfully
released to a total of 241 qualified beneficiaries, consisting of 206 college students, 30
postgraduate students, and five Licensure Examination reviewees. The assistance provided
financial support to help cover educational expenses and enable beneficiaries to continue their
academic and professional pursuits. This initiative reflects the company's commitment to
promoting access to education, supporting human resource development, and investing in the
long-term growth and success of students within the host community.
In addition, full scholarships were awarded to two Mining Engineering students under the
Development of Mining Technology and Geosciences, a core program of the Philippine Mines
and Geosciences Bureau, which provides structured funding for academic scholarships,
research and development, and technology transfer.
Infrastructure support
Construction of the second reservoir under the Ma-alinao Potable Water System Project was
completed. The additional reservoir is expected to improve water storage capacity, enhance
water distribution reliability, and strengthen the overall functionality of the community water
system. The Ma-alinao area contains the nearest community within the mine development
footprint.
Land access
The land access process in preparation for the construction and future operations of the MCB
Project is ongoing. During the Quarter, house-to-house information campaigns continued to be
conducted to provide community members with a clear understanding of the land access
process and to facilitate the endorsement of clan representatives, ensuring transparency,
inclusivity, and informed participation. Simultaneously, field validation activities for clan
boundary delineation are being carried out to verify and document clan ownership claims.
These efforts are essential in establishing an accurate basis for land access negotiations while
fostering trust, collaboration, and stakeholder engagement throughout the process.
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
12
The census and crop survey also commenced as part of the land access and validation process.
The activity aims to identify, document, and verify affected individuals, households, and
agricultural assets within the project area. Through systematic data gathering and field
validation, the survey establishes the basis for determining eligibility for compensation and
assistance while ensuring transparency and minimising the risk of fraudulent or ineligible claims.
The results will support the preparation of an accurate and defensible compensation framework
for project-affected persons.
Balatoc Cultural Heritage Baseline Study
The Balatoc Cultural Heritage was formally initiated with a series of field-based data gathering
activities, including Key Informant Interviews, Focus Group Discussions, and oral history
documentation sessions. These engagements sought to capture and preserve the community’s
cultural knowledge, traditions, practices, values, and historical narratives while ensuring that
Indigenous Knowledge Systems and Practices are appropriately documented and recognised.
The study intends to establish a comprehensive cultural heritage baseline for the Balatoc
Indigenous Cultural Community (“Balatoc ICC”), providing an essential reference for identifying,
assessing, and managing potential project-related impacts on cultural heritage resources.
Moreover, the initiative supports the integration of cultural heritage considerations into project
planning, management, and decision-making processes, thereby promoting the protection,
preservation, and continued respect for the community’s cultural identity and heritage.
Financial assistance
Various forms of financial assistance were extended during the quarter to support the welfare
and social development of the Balatoc ICC. These initiatives included the provision of honoraria
payments to Early Childhood Education Teachers in recognition of their role in nurturing young
learners, medical assistance to community members requiring healthcare support, and
bereavement assistance provided in accordance with local customs and traditions.
Financial support was also extended to the annual Sportsfest, a community-wide event that
fostered unity, strengthened social bonds, encouraged youth participation, and promoted the
preservation and appreciation of the cultural heritage and values of the Balatoc ICC.
Collectively, these assistance programs reflect MMCI's continuing commitment to enhancing
community well-being, supporting vulnerable sectors, and promoting inclusive and sustainable
social development.
MCB environmental management and ancillary permits
Environmental protection and enhancement program
Routine hydrogeological monitoring activities were carried out to support the ongoing
assessment of groundwater and surface water conditions within the project area. Weekly flow
rate monitoring was also conducted at Kafacrutan Creek to record discharge rates. These
monitoring activities provide valuable data for understanding groundwater and surface water
behaviour and their response to precipitation events.
ASX RELEASE | QUARTERLY REPORT | 30 June 2026
13
Ancillary permits
Continuous coordination and monitoring activities were undertaken with the National Water
Resources Board concerning the Conditional Water Permit. These efforts included regular follow-
through actions aimed at ensuring compliance with permit requirements and facilitating the
timely issuance of the Permanent Water Permit.
Botilao Copper-Gold Prospect, Philippines
No major field activities were undertaken during the Quarter, other than ongoing stakeholder
engagement.
Sagay Copper-Gold Project, Philippines
Key activities during the Quarter includ