Celsius collaborates with Kalinga LGU for MCB Road Access
Released
Released
Announcement PDF
ASX/AIM RELEASE
19 OCTOBER 2023
Celsius Collaborates with Kalinga LGU
for MCB Road Access
HIGHLIGHTS
• Memorandum of Agreement signed between Makilala Mining and the Kalinga
Provincial Government to jointly develop the road alignment for the MCB
Project’s access from mine site to port.
_______________________________________________________________________________
Celsius Resources Limited (“CLA” or “Celsius”) (ASX, AIM: CLA) is pleased to announce that its
Philippine subsidiary, Makilala Mining Company, Inc. (“MMCI” or “the Company”), has signed
a binding Memorandum of Agreement (“MOA”) with the Local Government Unit of the Province
of Kalinga (“LGU”) for the development of the access road for its flagship Maalinao-CaigutanBiyog Copper-Gold Project (“MCB” or “the Project”).
The MOA represents the commitment of both parties, MMCI and the LGU, to jointly undertake
the completion of the 84.5-kilometer Lubuagan-Batong Buhay-Abra Road Project (“Road
Project”) which will pass through the MCB Project area and parallel to its estimated road
alignment from the mine site to existing roads leading to its port of interest in Ilocos Sur.
Celsius Executive Chairman, Atty. Julito R. Sarmiento, said:
“In the development of the MCB Project, we have always consulted and partnered with the
local government to align our plans and programs for the efficient use of resources to achieve
a common goal. We are grateful that the Provincial Government, through the leadership of
Governor James Edduba, is receptive in collaborating with us to pave the way for the MCB
Project’s infrastructure needs, as well as those of the local communities.”
Kalinga Provincial Governor, James S. Edduba said:
“We are happy to collaborate with MMCI on the development of this Road Project. We are
envisioning that this Road Project, once implemented, will contribute to the sustainable and
inclusive economic growth and rapid progress of the Province of Kalinga, attract further
development opportunities, and major business investments for our constituents.”
Level 5, 191 St. Georges Terrace, Perth WA 6000 PO Box 7059, Cloisters Square PO, Perth WA 6850
P: +61 2 8072 1400 E: info@celsiusresources.com.au W: celsiusresources.com
Signing of the MOA at the MCB Project Area in Kalinga, Philippines,
with Kalinga Provincial Governor James S. Edduba and CLA Managing Director Peter Hume
Under the MOA, MMCI has agreed to fund the construction and development of approximately
21-kilometers of road alignment (“Road Alignment”) which is part of the Road Project, including
the development of the detailed design and construction plans of the road incorporating the
design criteria that should cover the minimum requirements to support the main construction
and full operation of the MCB Project, in close coordination with the LGU.
On their part, the LGU will obtain the necessary permits and approvals from the concerned
national and local government agencies and undertake land acquisition procedures in full
compliance with all relevant national and local laws, rules and regulations, including strict
adherence with Republic Act No. 3019 on Anti-Graft and Corrupt Practices Act and ethical
standards 1.
The funding guidelines of the MOA are as follows. MMCI will only release funding for each active
phase of the Road Alignment in accordance with an agreed schedule of the phases as follows:
i.
Detailed Engineering – The detailed engineering phase shall include the
development of a detailed scope of work for the construction of the Road Alignment
for the purpose of bidding. The LGU will deploy a survey team to conduct the
preliminary ground assessment of the Road Alignment, and MMCI will engage a
competent engineering firm or consultant to develop the detailed engineering and
construction drawings of the Road Alignment to determine the preferred alignment
and construction cost based on the outcome of the technical work.
1
RA 3019 is the main anti-corruption law in the Philippines. It enumerates certain acts of public officials that constitute graft or
corrupt practices, or which may lead thereto: https://lawphil.net/statutes/repacts/ra1960/ra_3019_1960.html
ASX/AIM RELEASE |
PAGE
2
ii.
Bidding and Awarding of the Road – This phase includes the tendering process, in
full compliance with the relevant laws, for the Road Alignment.
iii.
Construction – The Road Alignment construction will coincide with the development
of the MCB Project and be delivered in advance of major construction activities of
and based on a timeline and schedule provided by MMCI.
The actual financial impact of the binding MOA to the Company will be determined when the
Detailed Engineering phase has been completed, and the timeline for the Road Project and
Road Alignment will be determined as part of the agreed schedule of phases as detailed above.
The MOA shall remain binding until the obligations of both parties have been performed, unless
expressly terminated by mutual written consent between the parties. Termination of the MOA
shall be in writing and will take effect within thirty working days from receipt of the written notice.
The significance of the binding MOA to the Company is that it allows MMCI to have the most
appropriate Road Alignment to allow for the cost-efficient and safe transport of oversized and
overweight cargo, and concentrate products, during the construction, development and
operation stages of the MCB Project. In addition, it will allow MMCI access to use the nearest
port in Ilocos Sur to ship its concentrate products to during its operation and commercial
production stage of the MCB Project.
MCB COPPER-GOLD PROJECT
The MCB Copper-Gold Project (MCB) is located in the Cordillera Administrative Region in the
Philippines, approximately 320km north of Manila (Figure 1). It is the flagship project within the
Makilala portfolio which also contains other key prospects in the pipeline for permit
renewal/extension.
A maiden JORC Compliant Mineral Resource Estimate was declared for the MCB Project in
January 2021, comprising 313.8 million tonnes @ 0.48% copper and 0.15g/t gold, for 1.5 million
tonnes of contained copper and 1.47 million ounces of gold, of which 290.3 million tonnes @
0.48% copper and 0.15 g/t gold is classified as Indicated and 23.5 million tonnes @ 0.48%
copper and 0.10 g/t gold is classified as Inferred.
An updated JORC compliant Mineral Resource Estimate was announced for the MCB Project on
12 December 2022, comprising 338 million tonnes @ 0.47% copper and 0.12 g/t gold, for total
of 1.6 million tonnes of contained copper and 1.3 million ounces of gold, reported to a preferred
lower cut-off grade of 0.2% copper.
A Study for the MCB Project was announced by CLA on 1 December 2021, which identified the
potential for the development of a copper-gold operation with a 25-year mine life. The Study
was based on an underground mining operation and processing facility to produce a saleable
copper-gold concentrate.
Highlights from the Study include a Post tax NPV (8%) of US$464m and IRR of 31%, assuming a
copper price of US$4.00/lb and gold price of US$1,695/oz. Initial capital expenditure is
estimated to be US$253m with a payback period of approximately 2.7 years. The designed mine
production is matched to a 2.28Mtpa processing plant which will treat ore with an estimated
ASX/AIM RELEASE |
PAGE
3
average grade of 1.14% copper and 0.54g/t gold for the first 10 years of planned production
with a C12 cash costs at just US$0.73/lb copper, net of gold credits.
Figure 1. Location of the MCB Project in the province of Kalinga, Northern Luzon, Philippines.
Listing Rule 5.19 and 5.23 Disclosures
The Company confirms that it is not aware of any new information or data that relates to
Exploration Results and Mineral Resources at the MCB Project and that all material assumptions
and technical parameters underpinning the Mineral Resource continue to apply. The Company
notes that, as disclosed in this announcement and in previous announcements, a drilling
program is currently underway at the MCB Project the results of which will be incorporated into
an updated Mineral Resource in the future and that the current Scoping Study may provide new
assumptions and parameters for use in that Mineral Resource.
The Company confirms that all material assumptions underpinning the production targets and
forecast financial information in the Scoping Study continue to apply and have not materially
changed.
Forward Looking Statements
Some of the statements appearing in this announcement may be in the nature of forwardlooking statements. You should be aware that such statements are only predictions and are
subject to inherent risks and uncertainties. Those risks and uncertainties include factors and risks
specific to the industries in which the Company operates and proposes to operate as well as
general economic conditions, prevailing exchange rates and interest rates and conditions in the
2
C1 costs include all direct costs in mining, processing, general and administration, and selling (including freight).
ASX/AIM RELEASE |
PAGE
4
financial markets, among other things. Actual events or results may differ materially from the
events or results expressed or implied in any forward-looking statement.
No forward-looking statement is a guarantee or representation as to future performance or any
other future matters, which will be influenced by a number of factors and subject to various
uncertainties and contingencies, many of which will be outside the Company’s control.
The Company does not undertake any obligation to update publicly or release any revisions to
these forward-looking statements to reflect events or circumstances after today's date or to
reflect the occurrence of unanticipated events, except as required by law. No representation or
warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness
of the information, opinions or conclusions contained in this announcement. To the maximum
extent permitted by law, none of the Company’s Directors, employees, advisors, or agents, nor
any other person, accepts any liability for any loss arising from the use of the information
contained in this announcement. You are cautioned not to place undue reliance on any forwardlooking statement. The forward-looking statements in this announcement reflect views held only
as at the date of this announcement.
This announcement has been authorised by the Board of Directors of Celsius Resources Limited.
The information contained within this announcement is deemed by the Company to constitute
inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 as it
forms part of UK Domestic Law by virtue of the European Union (Withdrawal) Act 2018.
Celsius Resources Contact Information
Level 5, 191 St. Georges Terrace
Perth WA 6000
PO Box 7059
Cloisters Square PO
Perth WA 6850
P: +61 2 8072 1400
E: info@celsiusresources.com.au
W: www.celsiusresources.com
Celsius Resources Limited
Peter Hume
(Managing Director)
Multiplier Media
(Australia Media Contact)
Jon Cuthbert
ASX/AIM RELEASE |
P: +61 2 8072 1400
E: info@celsiusresources.com.au
W: www.celsiusresources.com
M: +61 402 075 707
E: jon.cuthbert@multiplier.com.au
PAGE
5
Tavistock Communications
(UK Media and Investor Relations)
Charles Vivian
Tara Vivian-Neal
+44 (0) 207 628 3396
M: 0044 7977297903
E: charles.vivian@tavistock.co.uk
M: 0044 7394408654
E: tara.vivian-neal@tavistock.co.uk
Beaumont Cornish Limited
(Nominated Adviser)
Roland Cornish/Felicity Geidt/Andrew Price
SP Angel Corporate Finance LLP
(Broker)
John Meyer/Ewan Leggat/Harry Davies-Ball